Tentative Water Street Schedule

Post date: Apr 09, 2019 5:44:56 PM

from the general contractor - subject to change:

The following dates should be pretty accurate for the remaining work on Rte 43.

    1. Re-mobilize to site on April 16, 2019.

    2. Granite curbing and concrete sidewalks 4/16/2019 to 5/15/2019.

    3. HMA binder at drives, raise castings, etc. 5/15/2019 to 5/24/2019.

    4. HMA surface course, tack, etc. week of 5/27/2019

    5. Loam, seed, HMA surface for driveways, lines striping week of 6/3/2019

    6. Punchlist, demobilization, etc. week of 6/10/2019

C & A and Darin will tweak this schedule for Tim as the work unfolds.