from the general contractor - subject to change:
The following dates should be pretty accurate for the remaining work on Rte 43.
Re-mobilize to site on April 16, 2019.
Granite curbing and concrete sidewalks 4/16/2019 to 5/15/2019.
HMA binder at drives, raise castings, etc. 5/15/2019 to 5/24/2019.
HMA surface course, tack, etc. week of 5/27/2019
Loam, seed, HMA surface for driveways, lines striping week of 6/3/2019
Punchlist, demobilization, etc. week of 6/10/2019
C & A and Darin will tweak this schedule for Tim as the work unfolds.