*156B Week 1
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Discussed construction methods and manufacturing under the new set of conditions. Designs will now focus less on prototyping and more on CAD analysis and simulations.
Accomplishments from Previous Week
Presented Risk Reduction Proposal
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Create CAD model for current design
Discuss Individual Component Analysis and how to apply it to refining our design
Finish Design Proposal Presentation
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor is willing to continue with project as planned.
Sponsor is willing to compromise on the 30 cm/s speed.
Should we be unable to achieve that speed, a tapping function can be installed on the brusher.
Sponsor is willing to let us remove the bristles from the brush if needed.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Project should still be doable under the current conditions
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Mechanism to attach the brush to the belts.
Access to facilities to manufacture and assembly the second iteration of the prototype.
Resources or Information Required but not Available
N/A
Schedule
Describe upcoming milestone
Begin CADing
Work on Design Proposal Presentation
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent $86.90
Aluminum rods, pulleys, bearings and belt for the risk reduction prototype.
Remaining $1013.10
Progress on Report and Webpage
Webpage updated up to Week 1 of 156B