Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finished poster
Obtained data more data from TEG and Hydroturbine testing
Accomplishments from Previous Week
Conducted closed loop testing for Hydroturbine
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish website- everyone
Finish Report- Everyone
Have a viable presentation for Class and Sponsor-Everyone
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Did not meet with sponsor this week
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Not to include every single detail we know in the poster, people will begin asking things we can't answer.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
No feedback yet
Risks and Areas of Concern
Not enough time to complete every test that we want
Resources or Information Required but not Available
N/A
Schedule
Work on poster based on feedback
Work on Presentation and cleaning up data for the presentation
Budget (list amount spent and amount remaining)
Progress on Report and Webpage