Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Code for multiple sensors in progress
Measurements and amount of PVC pipes needed in progress
Accomplishments from Previous Week
Testing of specs for hydroturbine
Obtained GPM from hydroturbine testing site (shower head.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Retest voltage and current from hydroturbine
Begin actual built for drip-irrigation system
Obtaindata for Thermogenerator
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Meeting Scheduled for Thursday.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Re-test specs for turbine, since no load had been added. 3/16
Providing a table with an overview of what was presented
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Better time management was obtained
Be a little clearer in explanation of designs
Risks and Areas of Concern
GPM of drip-irrigation system will not meet the minimum 5 gpm requirement.
One of the minimum requirements provided by our sponsor does not match our data, therefore must find mistake.
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Hydroturbines→$27.98
DMM→$22.97
Alligator Clips→$15.98
PVC Coupler→$3.40
PVC Pipe→$5.02
SD Card Reader→$6.45
Progress on Report and Webpage