Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Forming the project team
Meeting with the client for storming the project
Accomplishments from Previous Week
N/A
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Analyzing risk and assign individual component analysis - Ryan, Maverick, Peter, Dohwan
Assign individual responsibilities - Ryan, Maverick, Peter, Dohwan
Debrief and gain better objectives for project - Ryan, Maverick, Peter, Dohwan
Understand high priority of project - Ryan, Maverick, Peter, Dohwan
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Good to meet you
Short lecture about insulin injection devices
The client gaved us some samples of such devices
Next meeting through teleconference call
scheduled meeting (3/14 2:30pm)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Professor are not fully aware of project due to the confidentiality
suggested closely working with Dave
Commented good start and learn more about projectÂ
Risks and Areas of Concern
Confidentiality
Limited understanding of biomedical devices
Required upcoming steps for project
Resources or Information Required but not Available
CAD models
dimensions of needles / catheter
Client's previous work on the inserting device
Schedule
Describe upcoming milestone
Ideating a prototype
Update Gantt chart.
Yes
Budget (list amount spent and amount remaining)
Spent: $0
Available: $700
Total Budget: $700
Progress on Report and Webpage
Report has been updated on the webpage, however other pages have not been updated due to confidentiality