Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Accomplishments from Previous Week
Ordered Fluon
Increase cold kP from 1 to 5, only see more oscillations, but no change in the rise time. Therefore, we suspected that it's a system limit. Minimum rise time was 1.8s.
Modified PID code with integral windup solution.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Build control unit case, separate heat sink and fan (canjie, Quanxing)
continue tuning the PID controller, in order for the system to reach temperature set point at a faster rate (Irene, Jinchang)
webcam holder design and assembly (Irene)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
can use fluon on the sides of the chamber to pretend the fly from walking on the sides.
prefer cooling fan over ice water pool, but need to reduce noise and vibration caused by the fan.
Current venting of chamber was more than enough for 15min experiment. Can add 0.5 mm diameter hole for comparison
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
use integral windup code in 156A
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage