Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Fully familiarized with eye tracking program for immediate testing once prototype is finished.
Decided on one of two cameras to be used in the final prototype.
Working on mount for the eye camera.
Purchased all the potential cameras.
Accomplishments from Previous Week
Fabricated clip-on mount for world camera (forehead camera).
Researched additional information about head sizes of commercial glass frames.
CAD model of eye camera mount.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
3D print materials for clip-on part of the eye camera and CAD additional parts as needed. (Paul)
Create a slightly modified version of current gaze glasses frame as back up. (Seung-Hyo)
Troubleshoot programming (Kent)
Finish design and fabrication of eye camera holder. (Team)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Liked goose-neck idea for the eye camera holder. (1/31/2014, in person).
Will purchase a small size gooseneck for testing.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Check impedance control for USB cables.(1/30/2014, in person).
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None as of 1/302014 - 2/5/2014
Risks and Areas of Concern
Reduce the weight of wire and find smaller gauge USB cables.
Glass slipping from face while use.
Heat sink of world camera may get too hot.
Purchasing reliable glass frames at a reasonable price with our budget.
Resources or Information Required but not Available
Whether thinner gauge USB will have no effect in function.
Whether gooseneck has enough resistance force to stay stable once clipped on.
Schedule
Finish purchasing major components by Week 6.
Start 3D printing and hardware fabrication starting Week 6.
Testing of prototype after fabrication is complete.
Budget (list amount spent and amount remaining)
Amount spent: $737.77
Amount left: $4762.23
Progress on Report and Webpage
In the progress of updating website with new information of project progress.
Draft of report is being written for submission on Friday (2/7/2014).