Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Analysis: Mostly Completed
Actual motor torque-pulse requirement
Equivalent thrust on bearings
According to GeckoDrive, the half-step and micro-step torque-speed curves are the same
Design: Completed
Fabrication: Waiting on belt clamp plate, shaft coupling (ordered, waiting to arrive)
Tests: Waiting for non-magnetic screws to arrive to test for distortion in MRI
Accomplishments from Previous Week
Drilled and tapped hole pattern on mounting plate
Purchased nylon screws for mock tooling
Debugged stop button, motor disabled button in LabVIEW, digitalRead for limit switches and current sensors
Connected and debugged limit switches in LabVIEW
Completed assembly drawings with part numbers and high-resolution CAD
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Perform time and distance tests to see if carriage moves as expected (Ola, Brian, Sally)
Have PCB ordered, complete fiber optic communication (Alex)
Replace limit switches with optical sensors and debug if necessary (Brian)
Complete assembly with belt end clamp (Ola, Sally)
Finish updating webpage (Sally)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Hole pattern on mounting base, 1" spacing from the center (Mark, 5/15)
Completed, attached to the carriage
Consider using Scotch-Brite to create satin finish on the aluminum parts (Mark, 5/15)
Approved mechanical design, robust (Mark, 5/15)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Bearing Analysis - Equivalent Thrust (in person, 5/15)
Used sum of moments to determine equivalent thrust on one ball bearing
Maximum thrust: approximately 3.92 lbs
Maximum thrust capacity on one ball: approximately 9.14 lbs
Conclusion: reaction forces created by moment well within range
Bring completed design to show sponsor
Showed Mark, who is in charge of fabricating parts for the CFMRI
Sponsor, Robert, was unavailable that week but we will be presenting it to him Thursday, 5/22
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Professional version of LabVIEW is required to create an .exe file, which is available in Steve Robert's lab (via email, 5/14)
Note: .exe files run faster than original LabVIEW file
Risks and Areas of Concern
Fiber optic connections
ordering fiber optic cable, PCB
Optical sensors
ordering reflective photologic sensors (order sent, but not processed yet)
Resources or Information Required but not Available
None
Schedule
Prototype with fiber optic communication
Update Gantt chart.
Budget (list amount spent and amount remaining)
Total: $1500
$502.24 spent, $997.76 remaining
Progress on Report and Webpage
Report
revisions based on comments on the first draft
'impact on society' section in progress
began compiling the appendix
Webpage
revisions to front page based on critique
uploaded files under 'Multimedia'
updated budget and parts under 'Reports'