N/Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Solidified Project Goals
Accomplishments from Previous Week
Meet sponsor
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Use the 3D scanner to scan a similar flower
Learn and get familiar with the Z-brush software
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Outlining of Project Goals
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
N/A - This week was the first meeting
Risks and Areas of Concern
Undercutting in CNC
Technological limitations in scanning and printing
Resource availability
Conditions of final survey area
Resources or Information Required but not Available
N/A
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
0 Spent
2000 Remaining
Progress on Report and Webpage
None