Overview of Status of Analysis, Design, Fabrication, Tests, etc.
This week is focused on completing all hardware
All mounts are in the completion phases of fabrication
New microscope tests including the use of ND filters are to take place
Post processing of images will follow if necessary
Will be going to BD San Jose this coming Monday for sponsor presentation
Accomplishments from Previous Week
First tests with new Dinolite microscope completed with mediocre results
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Microscope mount and bracket fabricated and anodized (Kevin)
Attain images from new tests and post process if necessary (Justin)
Bracket adjusted and anodized (Carlos)
Complete fabrication of second prototype of LED filters (Daniel)
Complete sponsor presentation
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Make sure to discuss on how we got to where we were – constant changing requirements from a crazy sponsor, different feedback from different functions, etc?
Lessons learned – what did you guys learn? If you were to redo this project, what would you have done differently?
Where to go from here – if you were to hand this off to the next student group, or off to me, what would be the next steps?
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Clarify the pinhole illumination slide with entire system model/description
Annotate all images
Present an explanation of method behind software
Present a list of alignment steps that the FSR needs to follow
For final presentation, include tolerances and results of variability tests (e.g. microscope position/lighting conditions)
Risks and Areas of Concern
Results from ND filter tests determines system usability on FACSAria system
Low light sensitivity issues on FACSCanto system
Resources or Information Required but not Available
N/A
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$1124 spent
$875 remaining
ND filter cost to be factored in
Progress on Report and Webpage
Report comments to be received and edited
Same for webpage