Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Composite frame and enclosure designs finalized.
Epoxied ESC's successfully tested
Accomplishments from Previous Week
Test flight successful
Preliminary Float testing performed
ESC's thermally coated
Finalized design
Rapid prototyped a test mold
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Print 3D mold of housings (Vik)
New float design testing (Sheryl)
Get enclosure plates machined (Matt)
Complete purchasing of layup materials (Efrain)
Rapid prototype motor plates (Richard)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Proposed wider stance of floats to improve stability
Positioned floats further out and tested 4/29
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Use expanding spray foam for floats - 4/24
Use plastic automotive fasteners for housing - 4/24
Orientation of the floats should have minimum impact on aerodynamics - 4/24
Place under pusher motors
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Students were wondering if we could actually get the copter to fly
Completed test flights over the weekend 4/14
Risks and Areas of Concern
Float design
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent: 1,671.25
Remaining balance: 1,828.75
Progress on Report and Webpage
Continue to update multimedia and front page on website
revised parts previously worked on, continue to input new parts on report