Overview of Status of Analysis, Design, Fabrication, Tests, etc.
In process of prototype assembly
Upcoming flight test
Accomplishments from Previous Week
Finished carbon fiber layup
Soldered wires for connections
1st poster draft completed
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Prototype assembly (Richard)
Test flight with prototype (group)
Record videos from testing (Sheryl)
Revise report (group)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
possible ocean flight test on Wednesday of 10th week (5/30/13) -in person
finishing flight-ready prototype
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
should have flight test before going to ocean (5/30/13) -in class
finishing assembly for flight testing before Wednesday
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
look at saving wight by using a thin plastic filled with air for floats (5/22/13) -in person
perhaps lessen the words on final design slide (5/22/13) - in person
use silicon spray instead of WD-40 for water repellent on motors (5/22/13) - in person
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent: $2088.78
Remaining: $1411.22
Progress on Report and Webpage
Report: filling in more analysis and prototype performance
Website: filling in prototype performance and clean up formatting