Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Ordering basic parts
Finalizing design
Accomplishments from Previous Week
Initial design/CAD Model
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Begin adjusting design to specific components
Order primary components
DC Motor
Encoders
Propellers
Shaft
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Better definition of functional requirements
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Having a high powered motor able to lift the shaft and helicopter
Powering the propeller motors
Budget due to cost/quantity of sensors
Resources or Information Required but not Available
Schedule
Assemble prototype
Determine required high speed motor
Budget (list amount spent and amount remaining)
$0 spent
Progress on Report and Webpage
Updated progress report for 156B Week 1
Updated Team Member page