v3 Preview Admin Console task list


GlassFish v3 Preview Admin Console Task List

Important Dates:   

M2 - JavaOne Feature Freeze                           4/20/2009
EA HCF - only showstoppers fixes after this      5/4/2009

Committed delivery for JavaOne Release
  •  Finish GUI one pager for review
  • All pages converted to use xhtml template
  • General page layout, promotion frame etc
  • Navigation tree functioned with tree node highlight, expense & collapse, refresh etc.
  • Pluggability API (that doesn't tie to woodstock)  and implementation.
  • Code to support switching to use HTTP API
  • Grizzly Configuration
  • Re-do HTTP Service and related pages that has dtd changes due to Grizzly
  • Generic Application  Deployment and Listing
  • JavaOne HOL
  • JavaOne BOF
  • Dashboard
  • Ad Hoc Monitoring using scripting  (nice to have,   depending on backend)
  • MQ Config (nice to have)
  • Transaction Service configuration (nice to have)
  • Connector Connection Pools (NTH)
  • Resource Adapter (NTH)



Tasks to be completed for EA HCF by each developer

** In addition to the task listed below,  all developer will be spending time with Jim Berney to provide information and discussion.
     Bug Fixes is not listed below, but will also takes up developer's time.


 Owner Task #         
Task 
 Duration
 Start Date
 Status Dependencies
 Anissa
Lam
 L1 
 Finish GUI one pager for review
 2 weeks
  DONE 
  L2

Provide list of commands or equivalent to Rajeshwar
 1 day
  DONE 
  L4Grizzly Configuration Support
   -- Screen Design
   -- Implementation
 10 days
  DONE
 Grizzly Integration,  HTTP API
  L5
Redesign  and implement  the current HTTP Service/Listeners/Virtual Server pages according to the new dtd from Grizzly config.


 7 days
  DONE Grizzly integration
  L6 Application Pages
  -- Deployment for all apps
  -- Listing submodules
  -- Listing sniffer


 8 days

 DONE Input from HIE
  L7     Java One HOL


 10 days
  DONE 
  L8

Transaction Service
 1 day
  DONE
 
  L9

 Connector 3 days
  0% 
  L10

Resource Adapter
 2 days
  0% 


 Owner    Task #
Task
Duration
Start Date
Status
Dependencies
 Ana Caballero
 
C1
 Convert the 7 remaining pages to use xhtml (issue# 7334 )

    
  C2 Dashboard (iGoogle Like Page)
    HIE Input

** Ana will delivery either the Dashboard Page or the Monitoring Task

  C3


Ad Hoc Monitoring Using Scripting
    HIE Input

** Ana will delivery either the Dashboard Page or the Monitoring Task


 Owner    Task #
Task
Duration
 Start Date
Status
 Dependencies
 Jason Lee    
 J1 Merge v3-new-gui to Trunk
   DONE 
  J2 Navigation Tree Task
  - Redesign investation
  - Treenode highlight
  - Treenode refresh
  - Expense & colapse

    
  J3


 General page layout,  promotion frame
    depends on HIE input
  J4HTTP API Task:
  - Connections to backend
  - Utilities  for parsing JSON object returned so that can be used by all pages

    
  J5
 MQ Config

    This is Nice to Have Feature
  J6
JavaOne BOF
 
    


 Owner     Task #
 Task 
 Duration
Start Date
 Status Comments/Dependencies
 Ken Paulsen
 K1 Plugin Design & Implementation 15 Days
 3/17 Scoping work
 
  K2 HTTP API task:
     Identify what needs to be done in GUI code while waiting for backend


 10 Days
   * Path-name support
 * AMX functionality exposed via HTTP
  K3    JavaOne HOL 60% complete
 
 6 man-days
 3/16     
DONE
 
  K4Java One HOL  100% Complete


 30 man-days
  DONE