Campus Expansion

This page is maintained for the purposes of providing the latest and most relevant materials presented during Board Meetings and Outreach on the New Campus Expansion. Materials will be posted as soon as available following an editing process.

Stay up to date by attending: 

Campus Expansion Frequently Asked Questions

Yu Ying Growth Plans (Last updated: March 28, 2024)

Q: Why is Yu Ying expanding?

A: For nearly 10 years, Yu Ying has pursued its growth dreams in response to:


To accommodate our current student population, we had to repurpose some office spaces and amenities at Taylor Street into classrooms. A second campus will enable students, faculty, and administrative staff to better achieve our educational potential.


Since 2017, the Board of Trustees committed to implementing an inclusive, strategic growth plan. Working closely with school leaders, the Board has methodically moved the school, faculty, and caregiver community through multiple expansion requirements, including green-lighting criteria, and ultimately taking action by pairing with Washington Latin to purchase the Kirov campus.  


Of course, any expansion requires additional funding. As a public charter school, Yu Ying relies heavily on per-pupil revenues from the city. So, additional students bring additional funding. And, a new facility will enable us to offer Yu Ying’s unique educational  model, with both English and Chinese instruction, to more students. 


For more details and explanation of the Why Grow story, please see the recording of the November 30 Admin Coffee / Parent Town Hall.


Q: How many new students do we expect in Fall 2024?

A: March 28 update: In consideration of the construction schedule and programmatic considerations, the school submitted plans to MySchool DC to add 61 new learners in SY24-25, for a total student body of 691. 


This is a current reduction from the previous plan, which projected a total of 719 students for the upcoming school year.  The lower student enrollment allows us to continue to honor our growth plans, serve more students and build a strong ECE foundation while accounting for more restrictions on space.


Q: Why not delay opening the new facility until the 2025 school year? 

Construction updates and Status (Last updated: March 28, 2024)

Q: What is the current best estimate of when the second campus will be finished?

A: As a team, we have been working towards an August 2024 opening date as an aggressive option requiring many things to go smoothly.  Since that decision, some things have clicked into place while others, including a two month delay to access the site, permitting and weather have not.  

The latest schedule from our construction partner, Gilbane, still has a completion date in late August, but does not yet reflect milestones missed in Jan and Feb. We are currently about four weeks behind schedule. We are actively preparing contingency swing space for 4-15 weeks of delay, and will closely monitor construction progress through April to make a final determination of swing space timing and need in May.

March 1 Update: The permit has been secured, foundation work is almost complete; the first slab was poured on 2/9. Long lead time items are tracking on scheduling, which is good news for avoiding downstream delays.

March 28 Update: 

Q: What is the current best estimate regarding the need for the use of a temporary space?

A: The construction schedule was ambitious from the beginning. There was a delayed start due to site access and permitting delays. In addition, we’ve had some snow accumulation and possibly more unpredictable weather this winter. As a result, there is a high likelihood of delay to completing the project. 

Yu Ying continues to prioritize 1) securing high-quality contingency swing spaces for as long they may be needed and 2) safely completing the construction as quickly as possible to minimize swing space use.

Q: How will students in the new campus be kept safe with construction of Washington Latin’s campus underway during SY 24-25?

A: The building contractor and project management teams have extensive work experience in school settings. Construction schedules will be coordinated to put the noisiest periods outside of school hours, and a variety of safety barriers (like fencing and site access controls) will be put in place to keep students and others away from any construction hazards.  We will also work in close coordination with MCN’s site leader and Latin’s administration to complete daily safety checks and walkthroughs.  

For examples and more discussion of this point, please see the November 2023 Board meeting minutes/slides

Contingency Planning (Last updated: March 28, 2024)

Q: What is the current planned contingency measure?

Following extensive due diligence research, negotiations, risk assessments, costing analysis, and community engagement of several options from July 2023 to March 2024, the Board of Trustees approved a recommendation from the Board’s Growth Committee at the March 12, 2024 Board of Trustees meeting to utilize a contingency plan for Fall 2024 by:

Q: What was considered during the decision making process for this contingency measure? 

Based on this criteria, the Growth Committee considered, but ruled out the following options in favor of the on-campus trailers:

For more details on the analysis, please refer to the March Board of Trustees Materials.

Q: What grade levels will be affected? 

At present, this contingency plan will impact two sections of fifth graders, who will move into the trailers temporarily for the duration of the delay only.

Q: Are you considering virtual learning? 

March 28 Update: In light of the above contingency plan, virtual learning will not be used for the SY24-25 school year. 

Q: Are you considering a delayed first day of school?

March 28 Update: In light of the above contingency plan, a delayed start will not be used for the SY24-25 school year.

Archived FAQS

FAQS are moved from the above sections when they been supplanted by new information. THE INFORMATION BELOW IS OUTDATED AND KEPT FOR REFERENCE ONLY. 

Q: How many new students do we expect in Fall 2024? (ARCHIVE)

A: The original growth plan projected adding 85 new learners in SY24-25. However, depending on construction and contingency planning, this may change. The school will make a final determination regarding possible new students in line with My School DC deadlines this spring.

Q: When will you make a decision on contingency space options? (ARCHIVE)

The Board will review the recommended contingency space options and narrow the list to 2-3 finalists in February. A preferred option will be selected in March. However, it will be important to monitor how the construction schedule progresses throughout the spring. 

In May, the Board plans to determine whether a swing space is needed and for what length of time; if the Board determines the space is required, a contract will be initiated.

Decision-making timeline: 

March 1st update: Finalist options under negotiation are 1) Trailers on site at Taylor Street, 2) Existing Kirov Building 3) Full Floor of an Academic Hall at Catholic University. 

Q: What are the contingency options being considered? (ARCHIVE)

We have researched a wide range of swing space options in the immediate vicinity of the Taylor Street campus, including using existing or new trailers on-site. In reviewing space options, we are evaluating: 

Finalist swing spaces are all less than 1 mile from campus. At this time, we anticipate impacted students will maintain a Taylor Street drop-off to minimize any disruption to commutes or sibling convenience. 

We are currently exploring the possibility of swing space options at Catholic University, the existing Kirov Ballet Academy building and use of trailers at Taylor Street.  Details and terms with swing candidates will be shared in a limited fashion given the deliberative nature of each negotiation.  Further information will be provided to the community when feasible and appropriate, with our commitment remaining to provide the most information to those impacted the most.  We share information in a specified order to ensure the Board, staff and those most impacted get the information in a timely and more detailed way. 

Q: How may different grades be affected? (ARCHIVE)

Older students (grades 3-5) could be shifted with less impact to their academic programs and fewer space modification requirements, so we anticipate moving an older grade into contingency/swing space, if necessary. 

We do not anticipate moving any early childhood students into swing space. 

It is likely that one older grade will be moved to swing space for the temporary period, with their classrooms being used to house younger students, and then that grade will move back into 220 Taylor when the PK3, PK4, and K students are able to transition into the new campus building.  

Q: How can I share a suggestion for an alternate / swing space? (ARCHIVE)

At this time, we have high confidence and negotiations underway with 3 leading contender swing spaces. We do not anticipate pursuing additional options at this time.  

Q: If the start date changes, would it be the same for all grades? (ARCHIVE)

As stated above, a delayed school start date is unlikely to be needed as swing options are a more likely/viable option.  If we need to change the date for the first day of school, we would change it for all grades.  We will confirm the school calendar in the spring following our usual process, keeping families updated. 

Campus Expansion Meeting Materials

Consolidated materials from Admin Coffees, Town Halls, and Board meetings where Campus Expansion was discussed. Please refer to latest material for most up-to-date communications and status. Last updated: March 28, 2024

March 2024

February 2024

January 2024

December 2023

November 2023