UHS California Street Campus
Construction Update - May 2025
3150 California Street, San Francisco, CA
3150 California Street, San Francisco, CA
Construction Update Summary
In April, the General Contractor received the Temporary Certificate of Occupancy (TCO). The interiors are substantially complete at all levels, with the exterior finishes also substantially complete. The General Contractor will be finalizing their commissioning of all systems and inspections during the May period.
Typical construction noise is expected with these activities; however, the number of construction workers and noise has dramatically reduced now that the TCO is received. The General Contractor will continue to begin their standard workdays at 7:00 a.m., as permitted by the City. Saturday work may occur as needed to stay on schedule, while Sunday work will only be used as a last resort if unexpected delays occur.
Construction Lookahead
Over the remaining months of construction, the following activities will take place.
Commissioning of All Systems
Installation of Window Coverings
Construction Progress Photos
Overall view of the south facade as viewed from California Street.
Terrace finishes are substantially complete at Level 3.
Interior finishes at classrooms are substantially complete.
Finishes at the lobby are substantially complete, with installation of the donor glass also complete at the main staircase.
General Construction Notes
Please refer to the Site Logisitics Plan to the left regarding the most up-to-date information for circulation at the perimeter of the project site.