Drivers should take note that the northbound lanes of the Cutting/San Pablo intersection have been reconfigured to include one left turn lane instead of two.
Updated 4/18/25
Progress continues with sidewalk replacement, bike lane paving, curb and gutter forming, irrigation installation and electrical infrastructure installation. We have completed the bike lane buffer work through the east side of San Pablo Avenue and have made progress on the west side as well, including the sidewalk work near the San Pablo Ave. and Eastshore Blvd. intersection.
Our construction crews have transitioned to working in the center medians on San Pablo Ave. The work in the medians stretches from Knott Ave to Potrero Ave and is expected to be completed at the end of May. This means that construction activities will be performed on both sides of San Pablo Ave as well as in the center medians as we push to accelerate our progress.
Updated 3/21/25
Progress on the El Cerrito Del Norte Complete Streets project continues with the installation of sidewalk, buffer islands, irrigation lines, and streetlight foundations. The new buffer islands (shown below) will separate the bike lane from the general traffic lanes.
Beginning in the week of March 10th, the contractor began mobilizing on the west side of San Pablo Avenue as well. This means that construction activities will be performed on both sides of San Pablo Avenue at the same time to help complete the project sooner.
Demolition of thick, reinforced concrete and installation of new buffer islands during end of February, 2025.
The contractor has continued replacing sidewalks, installing irrigation lines, installing foundations for decorative streetlights, adding electrical conduits for traffic signals, and began making preparations for the new bikeway concrete buffers.
Digging and backfilling a trench with concrete for new traffic signal conduits and irrigation lines at Hill Street and San Pablo Ave on Jan 29, 2025.
Trenching and electrical conduit installation for streetlights and traffic signals at Hill Street and San Pablo Ave on Jan. 10, 2025.
Cage installation (left) & concrete placement (right) for traffic signal pole L foundation at Hill Street & San Pablo Ave on Nov. 19, 2024.
Construction crews recently removed trees and demolished portions of the sidewalk on northbound San Pablo Avenue. New trees will be planted in future stages. The new trees and sidewalks will improve pedestrian safety and comfort while improving the overall appearance of the corridor.
Sidewalk improvements and new tree planters being added on Hill Street.
Streetlight and pedestrian lighting work has also begun, with foundations being dug and poured for new light poles and new electrical infrastructure to be installed soon. This will improve the illumination for pedestrians and motorists.
New bus stop island on northbound San Pablo Ave. at Potrero Ave. Between the bus stop island and the sidewalk will be a new Class IV bike lane.
Workers Install a reinforced section of San Pablo Avenue in preparation for a new bus stop.
Sawcutting the existing pavement to prepare for demolition of existing pavement to construct new Class IV bike lanes.
Trenches for wiring up the improved traffic signals and bus shelters.
Please slow down while driving through the construction area, and be mindful of safety for workers, pedestrians and bicyclists.
For questions or comments about this project, contact:
Email: transformingdelnorte@gmail.com
Project hotline: 800-930-3720
For project updates or to send us questions and comments, please contact transformingdelnorte@gmail.com.
To attend future events about the El Cerrito Del Norte TOD Complete Street Improvement Project, please see below for dates and details.
No upcoming events planned
Mayfair Station 11600 San Pablo Ave.
Tabling outside Bart Station to share project information and updates, hear the community's valued thoughts and opinions, and to answer questions.
Environmental Quality Committee
Presentation to the Chamber of Commerce Board
El Cerrito Plaza TOD Event at El Cerrito Plaza (BART Station)
Presentation to Economic Development Committee
The El Cerrito del Norte Transit Oriented Development (TOD) Complete Streets Project's March 6th, 2024 groundbreaking ceremony was a huge success!
The City of El Cerrito hosted a groundbreaking ceremony for the El Cerrito del Norte Transit Oriented Development (TOD) Complete Streets Project on Wednesday, March 6, 2024, at 10:00 am. This celebratory event took place in front of the Mayfair Station development located at 11600 San Pablo Avenue, El Cerrito, CA 94530.
Speakers included: Director of Public Works, Yvetteh Ortiz; Mayor Tessa Rudnick, Councilmember Paul Fadelli, Lamar Hernadez-Thorpe, Mayor of the City of Antioch BART Director Rebecca Saltzman, and Robert Rogers from Alameda County Supervisor’s Gioia’s office, Ilaf Esuf from Buff Wick’s office (CA Assembly).
The Reliant Group, developers of the Mayfair Station hosted the event, and Jesus Vargas from VSCE was emcee.
The City hosted a booth for the del Norte TOD Complete Street Improvement Project at its annual 4th of July Festival at Cerrito Vista Park, to share information about the multi-modal improvements the project will implement. The booth received a lot of visitors who expressed excitement about the proposed project improvements and shared their ideas on the enhancements they would like to see in the project area. Director of Public Works, Yvetteh Ortiz, and consultant team members from CSW | ST2 and WRT were at the booth to answer questions about the project.
Topics of interest included intersection improvements, bike infrastructure and safety, signals, landscaping, sidewalk improvements, parking and accessibility, access to BART, and more. The kids engaged in fun coloring and art activities and learned about street design!
Visitors also took an online survey to provide additional feedback. - results of the survey will be updated soon.