Founder & Engineering Director
Propulsion:
Ox Tank RE
GSE Fluids RE
Expected Test Operations Timeline:
Hydrostatic Test [April 2026]
Cold Flow Test [April 2026]
Static Fire(s) [May 2026]
Wet Dress Rehearsal [June 2026]
I am updating this section as things progress! All work shown here is my own but program wide work can be shown if requested.
This is the first time the vehicle has been stacked to get weight estimates, update sims, and check fits. [15ft Long | 5in Diameter]
All parts here I have personally, designed, manufactured, and tested.
[UPDATING WITH NEW ONE] Updating drawings as project progresses and revisions are made.
Engineering Directors: Teddy Polkosnik, Noel Kim, Karan S
NASA USLI: Developed a COTS Solid rocket on a L1520 to deliver an experimental payload to the dedicated altitude.
Result: Unable to go to competition.
Subscale Attempt 1: Recovery failure due to electronics failure
Subscale Attempt 2: Low thrust to weight ratio
Full-scale Attempt 1: Recovery failure due to improper electronics setting
Full-scale Attempt 2: CATO
Fixed: Before taking on the hybrid rocket program we have eliminated all of these issues on our subscale demonstrator - Pathfinder [November 2024]