Project Updates
Feb. 1, 2023 - Feb. 28, 2023
Completed Work:
Demoed a portion of the existing concrete inside the VIP locker room area.
Demoed existing underground plumbing and rerouted plumbing lines at the new VIP locker room area.
Installed walls at the new VIP locker room and nutrition area.
Began overhead rough-ins at the nutrition area.
Installed decking, formwork, and reinforcing ahead of the 2nd floor concrete deck pour for the new addition.
Poured the 2nd floor concrete deck at the new addition.
Striped formwork at the concrete deck.
Began underground plumbing rough-ins at the new addition
Continued backfilling around the exterior walls of the new addition
Began masonry walls for the mechanical room and storage area of the new addition.
Upcoming work for the month of February 2023
Install in-wall rough-ins at the VIP locker room and nutrition area
Continue overhead rough-ins at the nutrition area and VIP locker rooms
Begin hot and cold tub wall formwork and reinforcing and the new addition.
Complete masonry walls at the mechanical room and storage area of the new addition
Continue waterproofing and backfilling efforts along the exterior perimeter walls of the new addition.
Continue underground rough-ins at the new addition.
Prep and pour a portion of the slab on grade at the new addition.
Begin layout and framing walls at 1st floor of the new addition.
Jan. 1, 2023 - Jan. 31, 2023
Completed Work:
Installed grounding and bonding measures at the hydro pit area.
Prepared the hydro pit area for the concrete slab on grade pour.
Poured the slab on grade at the hydro pit area.
Formed and poured the deck at the hydro slab area.
Installed waterproofing and backfilled along the hydro pit walls.
Began demolition of walls and existing finishes inside the existing training area at the Kenan Football Center.
Began layout and overhead mechanical installation in the soon to be VIP locker room area.
Installed glass at the storefront openings inside the player’s lounge.
Applied finish coat of paint to the walls at the players' lounge.
Complete above ceiling inspections at the players’ lounge.
Installed light fixtures at the players’ lounge.
Installed ceiling tile and architectural ceiling inside the players’ lounge.
Installed final millwork and casework inside the players’ lounge.
Installed finished flooring inside the players’ lounge.
Installed furniture, televisions, and equipment inside the players’ lounge.
Received beneficial occupancy for the players’ lounge.
Upcoming work for the month of January 2023
Demo a portion of the existing concrete inside the VIP locker room area.
Demo existing underground plumbing and reroute plumbing lines at the new VIP locker room area.
Install walls at the new VIP locker room and nutrition area.
Install in-wall rough-ins at the VIP locker room and nutrition area
Install decking, formwork, and reinforcing ahead of the 2nd floor concrete deck pour for the new addition.
Pour 2nd floor concrete deck at the new addition.
Strip formwork for the decking once the concrete has cured.
Begin hot and cold tub wall form work and reinforcing.
Dec. 1, 2022 - Dec. 31, 2022
Completed Work:
Continued concrete wall pours for the new addition.
Installed waterproofing along the hydro pit area walls.
Backfilled walls along the hydro pit area.
Continued overhead mechanical, plumbing, and electrical rough-ins at the players' lounge.
Finished interior walls at the players’ lounge.
Hung and finished drywall ceilings in the players’ lounge.
Applied prime paint inside the player’s lounge.
Installed ceiling grid inside the player’s lounge
Installed interior storefront frames inside the players’ lounge.
Upcoming work for the month of December:
Install grounding and bonding measures at the hydro pit area.
Prepare the hydro pit area for the concrete slab on grade pour.
Pour the slab on grade at the hydro pit area.
Form and pour the deck at the hydro slab area.
Install glass at the storefront openings inside the player’s lounge.
Apply finish coat of paint to the walls at the players' lounge
Complete above ceiling inspections at the players’ lounge
Install light fixtures at the players’ lounge
Install ceiling tile and architectural ceiling inside the players’ lounge
Install finished flooring inside the players’ lounge.
Nov. 1, 2022 - Nov. 30, 2022
Completed Work:
Continue foundation installation for the new addition.
Continued concrete wall pours for the new addition.
Installed steel column extension at the existing shored column.
Continued overhead mechanical, plumbing, and electrical rough-ins at the players' lounge.
Continued inwall rough-ins at the players’ lounge.
Installed hollow metal frames at the player’s lounge.
Continued insulating and hanging interior walls in the players’ lounge.
Upcoming work for the month of November :
Continue foundation installation for the new addition.
Continue concrete wall pours for the new addition.
Continue finishing interior walls at the players’ lounge.
Begin priming finished walls at the players’ lounge.
Begin ceiling grid at the players’ lounge.
Oct. 1, 2022 - Oct. 31, 2022
Completed Work:
Perimeter shoring wall has been installed.
Existing column underpinning support installed.
Completed interior demolition in the existing players’ lounge area.
Began overhead rough-ins at the players’ lounge.
Began interior wall rough-ins at the players’ lounge.
Began interior wall framing at the players’ lounge
Began excavations for foundations at the new addition.
Upcoming work for the month of October:
Continue foundation installation for the new addition.
Continue interior metal stud framing at the players’ lounge.
Continue overhead mechanical, plumbing, and electrical rough-ins at the players' lounge.
Hang and finish drywall at the players’ lounge.
Sep. 1, 2022 - Sep. 30, 2022
Completed Work:
Installed 90% of the perimeter shoring wall.
Began existing column underpinning support
Began interior demolition in the existing players lounge area.
Completed overhead mechanical, electrical, and plumbing rough-ins at the existing football weight room.
Upcoming work for the month of August:
Complete perimeter shoring wall.
Begin foundations for the addition portion of the project.
Begin layout and interior wall framing at the existing players lounge.
Begin rough-ins at the players lounge areas.
Aug. 1, 2022 - Aug. 31, 2022
Completed Work:
Relocate existing irrigation feed.
Prepping for the site shoring.
Begin existing column support underpinning.
Begin installation of the perimeter shoring wall ahead of concrete foundations.
Installation of the overhead mechanical, plumbing, and electrical rough-in at the existing weight room.
Upcoming work for the month of August:
Install shoring across the entire site
July 1, 2022 - July 31, 2022
Completed Work
Site clearing and grubbing
Demolition of the existing terrace connecting to The Football Center
Demolition of the existing stairway and site retaining walls.
Installation of the new utility fire line.
Installation of the storm water catch basins and piping
Upcoming Work for the month of July
Relocate existing irrigation feed.
Prepping for the site shoring
Begin existing column support underpinning
Begin installation of the perimeter shoring wall ahead of concrete foundations.
Installation of the overhead mechanical, plumbing, and electrical rough-in at the existing weight room.