Project Updates
October 1, 2023 - October 31, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Installed Vent Piping & Hatches – Wet Well
Installed Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Abandonment of Existing Well
Set Channel Grinder
Installation of Interior Piping in Wet Well
Set Precast Electrical Building
Form & Pour Concrete Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Layout / Form / Pour Transformer Pad
Installation of Misc. Metals (Railings, etc.)
Re-established Existing Berm (New Trees, Topsoil, Seeding)
Installation of Vent Piping
Layout / Form / Pour Generator Pad
Installation of Interior Valve Vault Piping
Installed 8" Service Drain Piping
Installed 16" Force Main (Diesel Bypass) Piping
Installed Partial 12" Force Main (Diesel Bypass) Piping
Installed Partial 20" Force Main (Effluent) Piping up to Tie-In Location
Completed Interior Meter Vault Piping
Continue 16" Force Main (Influent) Piping up to Tie-In Location
Pressure Test Installed Yard & Vault Piping
Work scheduled for the month of October:
Begin Installing 2" Water Service
Tie-In 10" DIP Discharge Piping (Valve Vault to Wet Well)
Continue Electrical Work
Continue with Grout Filling / Fillets
Continue Concrete Pipe Supports
Continue Interior Coatings - Wet Well/Grinder/Influent Concrete Structure
Begin Pipe Coatings in Meter & Valve Vaults
Install Injection Quill for Odor Control
September 1, 2023 - September 30, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Installed Vent Piping & Hatches – Wet Well
Installed Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Abandonment of Existing Well
Set Channel Grinder
Installation of Interior Piping in Wet Well
Set Precast Electrical Building
Form & Pour Concrete Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Layout / Form / Pour Transformer Pad
Installation of Misc. Metals (Railings, etc.)
Re-established Existing Berm (New Trees, Topsoil, Seeding)
Installation of Vent Piping
Layout / Form / Pour Generator Pad
Installation of Interior Valve Vault Piping
Installed 8" Service Drain Piping
Installed 16" Force Main (Diesel Bypass) Piping
Installed Partial 12" Force Main (Diesel Bypass) Piping
Installed Partial 20" Force Main (Effluent) Piping up to Tie-In Location
Completed Interior Meter Vault Piping
Work scheduled for the month of September:
Continue 16" Force Main (Influent) Piping up to Tie-In Location
Pressure Test Installed Yard & Vault Piping
Begin Installing 2" Water Service
Tie-In 10" DIP Discharge Piping (Valve Vault to Wet Well)
Continue Electrical Work
Continue with Grout Filling / Fillets
Continue Concrete Pipe Supports
Continue Interior Coatings - Wet Well/Grinder/Influent Concrete Structure
August 1, 2023 - August 31, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Installed Vent Piping & Hatches – Wet Well
Installed Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Abandonment of Existing Well
Set Channel Grinder
Installation of Interior Piping in Wet Well
Set Precast Electrical Building
Form & Pour Concrete Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Layout / Form / Pour Transformer Pad
Installation of Misc. Metals (Railings, etc.)
Re-established Existing Berm (New Trees, Topsoil, Seeding)
Installation of Vent Piping
Layout / Form / Pour Generator Pad
Installation of Interior Valve Vault Piping
Work scheduled for the month of August:
Continue Yard Piping
Continue Interior Meter Vault Piping
Continue Electrical Work
Continue with Grout Filling / Fillets
Continue Concrete Pipe Supports
Continue Interior Coatings - Wet Well/Grinder/Influent Concrete Structure
July 1, 2023 - July 31, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Install Vent Piping & Hatches – Wet Well
Install Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Abandonment of Existing Well
Set Channel Grinder
Continue Installing Interior Piping in Wet Well
Set Precast Electrical Building
Form & Pour Concrete Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Layout / Form / Pour Transformer Pad
Installation of Misc. Metals (Railings, etc.)
Re-established Existing Berm (New Trees, Topsoil, Seeding)
Installation of Vent Piping
Layout / Form / Pour Generator Pad
Work scheduled for the month of July:
Continue Yard Piping
Continue Interior Valve & Meter Vault Piping
Continue Electrical Work
Continue with Grout Filling / Fillets
Continue Concrete Pipe Supports
Begin Interior Coatings - Wet Well/Grinder/Influent Concrete Structure
June 1, 2023 - June 30, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Install Vent Piping & Hatches – Wet Well
Install Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Abandonment of Existing Well
Set Channel Grinder
Continue Installing Interior Piping in Wet Well
Set Precast Electrical Building
Form & Pour Concrete Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Layout / Form / Pour Transformer Pad
Installation of Misc. Metals (Railings, etc.)
Re-established Existing Berm (New Trees, Topsoil, Seeding)
Installation of Vent Piping
Work scheduled for the month of June:
Continue Yard Piping
Continue Interior Valve & Meter Vault Piping
Continue Electrical Work
Continue with Grout Filling / Fillets
Concrete Pipe Supports
Layout / Form / Pour Generator Pad
Interior Wet Well Coatings
May 1, 2023 - May 31, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Install Vent Piping & Hatches – Wet Well
Install Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Abandonment of Existing Well
Set Channel Grinder
Work scheduled for the month of May:
Begin Yard Piping
Continue Interior Valve & Meter Vault Piping
Continue Installing Interior Piping in Wet Well
Install Precast Electrical Building
Form & Pour Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Continue Electrical Work
Continue with Grout Filling / Fillets
Layout / Form / Pour Generator Pad
Layout / Form / Pour Transformer Pad
March 1, 2023 - April 30, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wet Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Top Slab Decking & Rebar Installation
Install Vent Piping & Hatches – Wet Well
Install Influent Top Slab
Form & Pour Concrete Slab - Electrical Building
De-Mob Large Crane
Excavated & Set Precast Valve Vault
Excavated & Set Precast Meter Vault
Form & Pour Baffle Wall
Installed Slide Gates Inside Influent Structure
Excavated & Set Two Precast Electrical Handhole Boxes
Work scheduled for the month of April:
Begin Yard Piping
Continue Interior Valve & Meter Vault Piping
Continue Installing Interior Piping in Wet Well
Install Precast Electrical Building
Form & Pour Pads for Pump Bases
Set Pumps Inside Wet Well Structure
Set Channel Grinder
Continue Electrical Work
Abandonment of Existing Well
Continue with Grout Filling / Fillets
Feb. 1, 2023 - Feb. 28, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wett Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Back Filling
Pulled Sheeting
Work scheduled for the month of February:
Continue to Run Dewatering Pumps
Top Slab Decking & Rebar Installation
Install Vent Piping & Hatches – Wet Well
Install Influent Top Slab
Begin Yard Piping
Form & Pour Concrete Pads
De-Mob Large Crane
SPECIAL ANNOUNCEMENT
We have begun pulling sheeting out of the ground! This is a huge milestone as we near the completion of the project.
Jan. 1st - Jan. 31st, 2023
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wett Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Installation of the Manhole inside Sheeting
Testing of Structures
Work scheduled for the month of January:
Continue to Run Dewatering Pumps
Back Filling
Begin Pulling Sheeting
Top Slab Decking & Rebar Installation
Install Vent Piping & Hatches – Wet Well
Install Influent Top Slab
Dec. 1st - Dec. 31st, 2022
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wett Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Striping Forms
Work scheduled for the month of December:
Continue to Run Dewatering Pumps
Installation of the Manhole inside Sheeting
Testing
Back Filling
Begin Pulling Sheeting
Nov. 1, 2022 - Nov. 30, 2022
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Backfilled to elevation -11.50
Installation of Rebar for Wett Well & Channel Grinder Walls
Form and Pour Slab & Walls for Channel Grinder
Form and Pour Slab & Walls for Wet Well
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Work scheduled for the month of November:
Continue to Run Dewatering Pumps.
Striping Forms
Installation of Wet Well Bypass Wall Pipes
Installation of the Manhole inside Sheeting
Testing
Coating
Back Filling
Oct. 1 2022 - Oct. 31, 2022
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Formed and poured the wet well foundation slab.
Formed and poured first light of walls for wet well.
Backfilled to elevation -11.50
Form and Pour Slab for Channel Grinder
Form and Pour Second Lift of Wet Well Walls.
Dewater Wet Well
Removal of Third Steel Whaler (Bottom)
Work scheduled for the month of October:
Continue to Run Dewatering Pumps.
Installation of Wet Well Bypass Wall Pipes
Installation of Rebar for Channel Grinder Walls
Form and Pour First Lift of Wet Well Walls.
Sep. 1, 2022 - Sep. 30, 2022
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Excavation of the sheeted hole.
Formed and poured the wet well foundation slab.
Formed and poured first light of walls for wet well.
Backfilled to elevation -11.50
Work scheduled for the month of September:
Continue to Run Dewatering Pumps.
Form and Pour Slab for Channel Grinder
Form and Pour Second Lift of Wet Well Walls.
Dewater Wet Well
Installation of Pump Discharge Wall Pipes/Sleeves in Wet Well Walls
Begin Removal of Third Steel Whaler
Aug. 1, 2022 - Aug 31, 2022
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Installed concrete waler.
Drove sheeting inside the excavation.
Work scheduled for the month of August:
Continue to excavate the sheeted hole.
Forming and pouring the foundation slab.
Forming and pouring walls for pump station wet well.
Continue to run dewatering pumps
July 1, 2022 - July 31, 2022
Completed Work:
The second whaler has been installed.
Temporary power has been installed.
Work scheduled for the month of July:
Installing concrete waler.
Driving sheeting inside the excavation.
Excavating the sheeted hole.
Forming and pouring the foundation slab.
Forming and pouring walls for pump station wet well.
June 20, 2022 - July 1, 2022
T. A. Loving Company has finished driving the shoring system and have dug almost 15’ deep inside the cofferdam. A cofferdam is made by driving sheeting in the ground, in this situation the cofferdam is round. Once all the sheeting is in place, we begin excavating the dirt inside the cofferdam and installing whalers. During the next two weeks we will be putting the finishing welds on the braces for the second whaler and excavating the hole to the proper depth for the third whaler. Whalers are used to help support the sheeting as we excavate further into the ground. The first two whalers are made of steel and the third whaler will be made of concrete. We will also be completing the installation of the temporary power with Melton Electric and Duke Energy.
Please maintain awareness around the site entrance as dump trucks will continue to drive in and out of the site.