Project Updates
Jan. 1st - Jan. 31st, 2023
We will continue to work on North Front Street between Grace Street and Walnut Street.
Completed Work:
Grace St. to Chestnut St. (200 Block)
Demolition (Removal of Asphalt, Curbing, and Sidewalks)
Tree Removal
Installation of New Water Main, Sewer Main, and Storm Drain.
Installation/Connections of New Water, Sewer, and Fire Services.
Two water main tie-ins at the Grace Street intersection.
Installation of New Granite Curbing
Removed steps in front of Pour House
Concrete Flatwork –
Demo of Existing Sidewalks
Installation of New ADA Ramps
Installation of New Sidewalks
Installation of New Brick Pavers
Installation of New Brick & Concrete Crosswalks
Roadwork –
Grading/ABC Stone
Asphalt Paving
Asphalt Striping (Pavement Markings)
Electrical Work –
Removal of Existing Light Posts & Installation of Temporary Light Poles
New Underground Wiring
Installation of New Light Posts and Bollards
Irrigation & Landscaping (Small Plants/Shrubs, Mulch, and Trees)
Installation of New Tree Grates
New Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)
Road Re-Opened
Grace St Intersection - Opened to East-West Traffic
Grace St. to Walnut St. Intersection (300 Block)
Demolition (Removal of Asphalt, Curbing, and Sidewalks)
Tree Removal
Installation of New Sewer Main, Water Main & Storm Drain
Installation/Connections of New Water, Sewer, and Fire Services.
Three water main tie-ins at the Walnut Street intersection.
Installation of New Granite Curbing
Concrete Flatwork
Demo of Existing Sidewalks
Installation of New ADA Ramps
Installation of New Sidewalks
Installation of Driveway
Installation of New Brick Pavers
Installation of New Brick & Concrete Crosswalks
Roadwork –
Grading/ABC Stone
Asphalt Paving
Electrical Work –
Removal of Existing Light Posts & Installation of Temporary Light Poles
New Underground Wiring
Installation of New Light Posts and Bollards
Install Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)
Irrigation & Landscaping (Small Plants/Shrubs, Mulch, and Trees)
Installation of New Tree Grates
Still To Complete:
Upcoming work (Grace St. Intersection):
Install Electrical Control Panel
Complete Concrete Sidewalk Next to Control Panel
Upcoming work (Grace St. to Walnut St.):
Asphalt Striping (Pavement Markings)
Pressure Washing
Remove Temp. Driveway
Re-Open Road (Remove Traffic Control)
Dec. 1st - Dec 31st, 2022
We will continue to work on North Front Street between Grace Street and Chestnut Street.
Completed Work:
Grace St. to Chestnut St. (200 Block)
Installation of new Water Main, Sewer Main, and Storm Drain.
Two water main tie-ins at the Grace Street intersection.
Installation of new Water, Sewer, and Fire Services.
Installation of new Granite Curbing
Removed steps in front of Pour House
Concrete Flatwork
New ADA Ramps
Demo of Existing Sidewalks
Installation of New Sidewalks
Roadwork – Grading/ABC Stone
Asphalt Paving
Asphalt Striping (Pavement Markings)
Brick Pavers
Mid-Block Crosswalk
Crosswalks - Grace St Intersection
Tree Removal
Road Re-Opened
Grace St Intersection - Opened to East-West Traffic
Electrical Work (Underground Wiring, Light Poles Installation, etc.)
Irrigation & Landscaping (Small Plants & Shrubs, Mulch)
New Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)
Grace St. to Walnut St. Intersection (300 Block)
Demolition (Removal of Asphalt, Curbing, Street Signs)
o Tree Removal
o Traffic Control (Road & Intersection Closure)
o Installation of New Sewer Main, Water Main & Storm Drain
o Installation/Connection of New Water & Sewer Services
o Connection of Fire Services
o Removal Existing Light Posts
o Installation of Temporary Light Posts
o Installation of Granite Curbing
Demo of Existing Sidewalks along 300 Block
New Concrete Sidewalks along 300 Block
Installation of New Roof Drains
Abandon Existing Water Main
Water Main Testing
Water Main Tie-Ins
Still To Complete:
Upcoming work for the month of December (Grace St. to Chestnut St.):
Install Landscaping (Tree Grates and Trees)
Install Bike Racks
Install Electrical Control Panel
Upcoming work for the month of December (Grace St. to Walnut St.):
Concrete Flatwork (Driveway and ADA Ramps)
Install Crosswalks
Install Brick Pavers
Install New Light Posts
Roadwork – Grading/ABC Stone
Asphalt Paving
Asphalt Striping (Pavement Markings)
Irrigation & Landscaping (Small Plants, Shrubs, Trees, and Mulch)
Install Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)
Nov. 1, 2022 - Nov. 30, 2022
We will continue to work on North Front Street between Grace Street and Chestnut Street.
Completed Work:
Grace St. to Chestnut St. (200 Block)
Installation of new Water Main, Sewer Main, and Storm Drain.
Two water main tie-ins at the Grace Street intersection.
Installation of new Water, Sewer, and Fire Services.
Installation of new Granite Curbing
Removed steps in front of Pour House
Concrete Flatwork
New ADA Ramps
Demo of Existing Sidewalks
Installation of New Sidewalks
Roadwork – Grading/ABC Stone
Asphalt Paving
Asphalt Striping (Pavement Markings)
Brick Pavers
Mid-Block Crosswalk
Crosswalks - Grace St Intersection
Tree Removal
Road Re-Opened
Grace St Intersection - Opened to East-West Traffic
Electrical Work (Underground Wiring, Light Poles Installation, etc.)
Irrigation & Landscaping (Small Plants & Shrubs, Mulch)
New Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)
Grace St. to Walnut St. Intersection (300 Block)
Demolition (Removal of Asphalt, Curbing, Street Signs)
Tree Removal
Traffic Control (Road & Intersection Closure)
Installation of New Sewer Main & Services
New Storm Drain [patrial]
New Water Main & Services [patrial]
Upcoming work for the month of November (Grace St. to Chestnut St.):
Install Landscaping (Tree Grates and Trees)
Install Bike Racks
Upcoming work for the month of November (Grace St. to Walnut St.):
Continue installation of the Water Main, and Storm Drain
Remove Existing Light Posts
Install Temporary Light Posts
Connection of New Water Services.
Installation of Granite Curbing.
Demo Existing Sidewalks
Concrete Flatwork (Driveway, Sidewalks and ADA Ramps)
Roadwork – Grading/ABC Stone
Asphalt Paving
Asphalt Striping (Pavement Markings)
Irrigation & Landscaping (Small Plants, Shrubs, Trees, and Mulch)
Install Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)
Oct. 1, 2022 - Oct. 31, 20221
We will continue to work on North Front Street between Grace Street and Chestnut Street.
Completed Work:
New water main and sewer main has been installed.
Temporary light posts have been installed.
Completed the two water main tie-ins at the Grace Street intersection.
Install RCP Storm Drain.
Connection of New Water and Fire Services.
Granite Curbing installation.
Pour House Steps Removed.
Corner Concrete Sidewalks/ADA Ramps of Grace St. Intersection.
Roadwork – Grading/ABC Stone
First Lift (1.5") of Asphalt Paved on 200 Block
Mid-Block Crosswalk
3 out of 4 Crosswalks at Grace St Intersection
Grace St Intersection is Opened to East - West Traffic
Advanced to the next block and Walnut St Intersection
Tree Removal - 300 Block
New Concrete Sidewalks (Partial)
Brick Pavers (Partial)
Traffic Control (Road Closure) - 200 & 300 Block
Upcoming work for the month of October (Grace St. to Chestnut St.):
Second Lift (1.5") of Asphalt Paving on 200 Block
Continue to Demo Existing Sidewalks - 200 Block
Pour New Concrete Sidewalks - 200 Block
Asphalt Striping
Electrical Work (Underground Wiring, Light Poles Installation, etc.)
Continue to Install Brick Pavers
Irrigation & Landscaping
Install Site Furnishings (Sign Post, Signs, Parking Meters, Benches, etc.)
Upcoming work for the month of October (Grace St. to Walnut St.):
Traffic Control (Road Closure)
Demolition (Remove Asphalt, Curbing, Street Signs, Light Posts, etc.)
Begin Installation of New Water and Sewer Main.
Remove Existing Light Posts
Install Temporary Light Posts
Other Items to Follow:
Install New Storm Drain.
Connection of New Water Services.
Granite Curbing installation.
Concrete Flatwork
Roadwork – Grading/ABC Stone
Sep. 1, 2022 - Sep. 30, 2022
We will continue to work on North Front Street between Grace Street and Chestnut Street.
Completed Work:
New water main and sewer main has been installed.
Temporary light posts have been installed.
Completed the two water main tie-ins at the Grace Street intersection.
Install RCP Storm Drain.
Connection of New Water and Fire Services.
Granite Curbing installation.
Pour House Steps Removed.
Corner Concrete Sidewalks/ADA Ramps of Grace St. Intersection.
Roadwork – Grading/ABC Stone
Upcoming work for the month of September (Grace St. to Chestnut St.):
Asphalt Pavement
Demo Existing Sidewalks
Pour New Concrete Sidewalks
Asphalt Striping
Electrical Work (Underground Wiring, Light Poles Installation, etc.)
Install Brick Pavers
Begin advancing to the next block and Walnut St Intersection
Irrigation & Landscaping
Install Site Furnishings (Sign Post, Signs, Parking Meters, Benches, etc.)
Upcoming work for the month of September (Grace St. to Walnut St.):
Traffic Control (Road Closure)
Demolition (Remove Asphalt, Curbing, Street Signs, Light Posts, etc.)
Tree Removal
Begin Installation of New Water and Sewer Main.
Install Temporary Light Posts
Other Items to Follow:
Install New Storm Drain.
Connection of New Water Services.
Granite Curbing installation.
Concrete Flatwork
Roadwork – Grading/ABC Stone
Aug. 1, 2022 - Aug. 31, 2022
We will continue to work on North Front Street between Grace Street and Chestnut Street.
Completed Work:
New water main and sewer main has been installed.
Temporary light posts have been installed.
Completed the two water main tie-ins at the Grace Street intersection.
Install RCP Storm Drain
Upcoming work for the month of August (Grace St. to Chestnut St.):
Begin advancing to the Walnut St Intersection
Connect/Switchover New Water Services
Electrical Work (Underground Wiring, Light Poles, etc.)
Continue to install Granite Curbs
Continue roadwork – Grading/ABC Stone
Asphalt Pavement
Asphalt Striping
Remove Pour House Steps
Demo Existing Sidewalks
Pour New Concrete Sidewalks
Install Brick Pavers
Irrigation & Landscaping
July 1, 2022 - July 31, 2022
We will continue to work on North Front Street between Grace Street and Chestnut Street.
Completed Work:
New water main and sewer main has been installed.
Temporary light posts have been installed.
Completed the two water main tie-ins at the Grace Street intersection.
Upcoming work for the month of July (Grace St. to Chestnut St.):
Install RCP Storm Drain
Connect/Switchover New Water Services
Electrical Work (Underground Wiring, Light Poles)
Install Granite Curbs
Roadwork – Grading/ABC Stone
Asphalt Pavement
Asphalt Striping
Remove Pour House Steps
Demo Existing Sidewalks
Pour New Concrete Sidewalks
Install Brick Pavers
Irrigation & Landscaping
June 20, 2022 - July 1, 2022
We will continue to work on North Front Street between Grace Street and Chestnut Street.
To date we have completed:
· Street demolition from the intersection of Chestnut St. to Grace St.
· New sewer main and services have been installed.
· New water main has been installed.
o New water services have been laid out but not connected.
Two-week look ahead:
· New water main and services will be chlorinated and tested.
o New water services to be reconnected to the meter.
· Electrical
o Disconnect and remove the two existing light post near the intersection of Grace St.
§ Temporary lighting will be installed.
o Install underground conduit
o Install a new ITS pole
· Begin installing new storm drain boxes and pipes.
· Perform two water main tie-ins in the Grace St. intersection (night work).