Project Updates

Jan. 1st - Jan. 31st, 2023

We will continue to work on North Front Street between Grace Street and Walnut Street.

Completed Work:

  • Grace St. to Chestnut St. (200 Block)

    • Demolition (Removal of Asphalt, Curbing, and Sidewalks)

    • Tree Removal

  • Installation of New Water Main, Sewer Main, and Storm Drain.

  • Installation/Connections of New Water, Sewer, and Fire Services.

  • Two water main tie-ins at the Grace Street intersection.

  • Installation of New Granite Curbing

  • Removed steps in front of Pour House

  • Concrete Flatwork –

    • Demo of Existing Sidewalks

    • Installation of New ADA Ramps

    • Installation of New Sidewalks

  • Installation of New Brick Pavers

  • Installation of New Brick & Concrete Crosswalks

  • Roadwork –

    • Grading/ABC Stone

    • Asphalt Paving

    • Asphalt Striping (Pavement Markings)

  • Electrical Work –

    • Removal of Existing Light Posts & Installation of Temporary Light Poles

  • New Underground Wiring

  • Installation of New Light Posts and Bollards

  • Irrigation & Landscaping (Small Plants/Shrubs, Mulch, and Trees)

  • Installation of New Tree Grates

  • New Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)

  • Road Re-Opened

  • Grace St Intersection - Opened to East-West Traffic


  • Grace St. to Walnut St. Intersection (300 Block)

  • Demolition (Removal of Asphalt, Curbing, and Sidewalks)

  • Tree Removal

  • Installation of New Sewer Main, Water Main & Storm Drain

  • Installation/Connections of New Water, Sewer, and Fire Services.

  • Three water main tie-ins at the Walnut Street intersection.

  • Installation of New Granite Curbing

  • Concrete Flatwork

    • Demo of Existing Sidewalks

    • Installation of New ADA Ramps

    • Installation of New Sidewalks

    • Installation of Driveway

  • Installation of New Brick Pavers

  • Installation of New Brick & Concrete Crosswalks

  • Roadwork –

    • Grading/ABC Stone

    • Asphalt Paving

  • Electrical Work –

    • Removal of Existing Light Posts & Installation of Temporary Light Poles

  • New Underground Wiring

  • Installation of New Light Posts and Bollards

  • Install Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)

  • Irrigation & Landscaping (Small Plants/Shrubs, Mulch, and Trees)

  • Installation of New Tree Grates

Still To Complete:

  • Upcoming work (Grace St. Intersection):

  • Install Electrical Control Panel

  • Complete Concrete Sidewalk Next to Control Panel

  • Upcoming work (Grace St. to Walnut St.):

  • Asphalt Striping (Pavement Markings)

  • Pressure Washing

  • Remove Temp. Driveway

  • Re-Open Road (Remove Traffic Control)

Dec. 1st - Dec 31st, 2022

We will continue to work on North Front Street between Grace Street and Chestnut Street.

Completed Work:

  • Grace St. to Chestnut St. (200 Block)

    • Installation of new Water Main, Sewer Main, and Storm Drain.

    • Two water main tie-ins at the Grace Street intersection.

    • Installation of new Water, Sewer, and Fire Services.

    • Installation of new Granite Curbing

    • Removed steps in front of Pour House

    • Concrete Flatwork

      • New ADA Ramps

      • Demo of Existing Sidewalks

      • Installation of New Sidewalks

    • Roadwork – Grading/ABC Stone

    • Asphalt Paving

    • Asphalt Striping (Pavement Markings)

    • Brick Pavers

    • Mid-Block Crosswalk

    • Crosswalks - Grace St Intersection

    • Tree Removal

    • Road Re-Opened

    • Grace St Intersection - Opened to East-West Traffic

    • Electrical Work (Underground Wiring, Light Poles Installation, etc.)

    • Irrigation & Landscaping (Small Plants & Shrubs, Mulch)

    • New Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)

  • Grace St. to Walnut St. Intersection (300 Block)

    • Demolition (Removal of Asphalt, Curbing, Street Signs)

o Tree Removal

o Traffic Control (Road & Intersection Closure)

o Installation of New Sewer Main, Water Main & Storm Drain

o Installation/Connection of New Water & Sewer Services

o Connection of Fire Services

o Removal Existing Light Posts

o Installation of Temporary Light Posts

o Installation of Granite Curbing

    • Demo of Existing Sidewalks along 300 Block

    • New Concrete Sidewalks along 300 Block

    • Installation of New Roof Drains

    • Abandon Existing Water Main

    • Water Main Testing

    • Water Main Tie-Ins

Still To Complete:

  • Upcoming work for the month of December (Grace St. to Chestnut St.):

    • Install Landscaping (Tree Grates and Trees)

    • Install Bike Racks

    • Install Electrical Control Panel

  • Upcoming work for the month of December (Grace St. to Walnut St.):

    • Concrete Flatwork (Driveway and ADA Ramps)

    • Install Crosswalks

    • Install Brick Pavers

    • Install New Light Posts

    • Roadwork – Grading/ABC Stone

    • Asphalt Paving

    • Asphalt Striping (Pavement Markings)

    • Irrigation & Landscaping (Small Plants, Shrubs, Trees, and Mulch)

    • Install Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)


Nov. 1, 2022 - Nov. 30, 2022

We will continue to work on North Front Street between Grace Street and Chestnut Street.

Completed Work:

  • Grace St. to Chestnut St. (200 Block)

    • Installation of new Water Main, Sewer Main, and Storm Drain.

    • Two water main tie-ins at the Grace Street intersection.

    • Installation of new Water, Sewer, and Fire Services.

    • Installation of new Granite Curbing

    • Removed steps in front of Pour House

    • Concrete Flatwork

      • New ADA Ramps

      • Demo of Existing Sidewalks

      • Installation of New Sidewalks

    • Roadwork – Grading/ABC Stone

    • Asphalt Paving

    • Asphalt Striping (Pavement Markings)

    • Brick Pavers

    • Mid-Block Crosswalk

    • Crosswalks - Grace St Intersection

    • Tree Removal

    • Road Re-Opened

    • Grace St Intersection - Opened to East-West Traffic

    • Electrical Work (Underground Wiring, Light Poles Installation, etc.)

    • Irrigation & Landscaping (Small Plants & Shrubs, Mulch)

    • New Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)


  • Grace St. to Walnut St. Intersection (300 Block)

  • Demolition (Removal of Asphalt, Curbing, Street Signs)

  • Tree Removal

  • Traffic Control (Road & Intersection Closure)

  • Installation of New Sewer Main & Services

  • New Storm Drain [patrial]

  • New Water Main & Services [patrial]


  • Upcoming work for the month of November (Grace St. to Chestnut St.):

    • Install Landscaping (Tree Grates and Trees)

    • Install Bike Racks


  • Upcoming work for the month of November (Grace St. to Walnut St.):

    • Continue installation of the Water Main, and Storm Drain

    • Remove Existing Light Posts

    • Install Temporary Light Posts

    • Connection of New Water Services.

    • Installation of Granite Curbing.

    • Demo Existing Sidewalks

    • Concrete Flatwork (Driveway, Sidewalks and ADA Ramps)

    • Roadwork – Grading/ABC Stone

    • Asphalt Paving

    • Asphalt Striping (Pavement Markings)

    • Irrigation & Landscaping (Small Plants, Shrubs, Trees, and Mulch)

    • Install Site Furnishings (Signposts, Street Signs, Parking Meters, Benches, Trash/Recycle Bins, Bike Racks)


Oct. 1, 2022 - Oct. 31, 20221

We will continue to work on North Front Street between Grace Street and Chestnut Street.


Completed Work:

  • New water main and sewer main has been installed.

  • Temporary light posts have been installed.

  • Completed the two water main tie-ins at the Grace Street intersection.

  • Install RCP Storm Drain.

  • Connection of New Water and Fire Services.

  • Granite Curbing installation.

  • Pour House Steps Removed.

  • Corner Concrete Sidewalks/ADA Ramps of Grace St. Intersection.

  • Roadwork – Grading/ABC Stone

  • First Lift (1.5") of Asphalt Paved on 200 Block

  • Mid-Block Crosswalk

  • 3 out of 4 Crosswalks at Grace St Intersection

  • Grace St Intersection is Opened to East - West Traffic

  • Advanced to the next block and Walnut St Intersection

  • Tree Removal - 300 Block

  • New Concrete Sidewalks (Partial)

  • Brick Pavers (Partial)

  • Traffic Control (Road Closure) - 200 & 300 Block


Upcoming work for the month of October (Grace St. to Chestnut St.):

  • Second Lift (1.5") of Asphalt Paving on 200 Block

  • Continue to Demo Existing Sidewalks - 200 Block

  • Pour New Concrete Sidewalks - 200 Block

  • Asphalt Striping

  • Electrical Work (Underground Wiring, Light Poles Installation, etc.)

  • Continue to Install Brick Pavers

  • Irrigation & Landscaping

  • Install Site Furnishings (Sign Post, Signs, Parking Meters, Benches, etc.)


Upcoming work for the month of October (Grace St. to Walnut St.):

  • Traffic Control (Road Closure)

  • Demolition (Remove Asphalt, Curbing, Street Signs, Light Posts, etc.)

  • Begin Installation of New Water and Sewer Main.

  • Remove Existing Light Posts

  • Install Temporary Light Posts

  • Other Items to Follow:

  • Install New Storm Drain.

  • Connection of New Water Services.

  • Granite Curbing installation.

  • Concrete Flatwork

  • Roadwork – Grading/ABC Stone

Sep. 1, 2022 - Sep. 30, 2022

We will continue to work on North Front Street between Grace Street and Chestnut Street.

Completed Work:

  • New water main and sewer main has been installed.

  • Temporary light posts have been installed.

  • Completed the two water main tie-ins at the Grace Street intersection.

  • Install RCP Storm Drain.

  • Connection of New Water and Fire Services.

  • Granite Curbing installation.

  • Pour House Steps Removed.

  • Corner Concrete Sidewalks/ADA Ramps of Grace St. Intersection.

  • Roadwork – Grading/ABC Stone


Upcoming work for the month of September (Grace St. to Chestnut St.):

  • Asphalt Pavement

  • Demo Existing Sidewalks

  • Pour New Concrete Sidewalks

  • Asphalt Striping

  • Electrical Work (Underground Wiring, Light Poles Installation, etc.)

  • Install Brick Pavers

  • Begin advancing to the next block and Walnut St Intersection

  • Irrigation & Landscaping

  • Install Site Furnishings (Sign Post, Signs, Parking Meters, Benches, etc.)


Upcoming work for the month of September (Grace St. to Walnut St.):

  • Traffic Control (Road Closure)

  • Demolition (Remove Asphalt, Curbing, Street Signs, Light Posts, etc.)

  • Tree Removal

  • Begin Installation of New Water and Sewer Main.

  • Install Temporary Light Posts

  • Other Items to Follow:

    • Install New Storm Drain.

    • Connection of New Water Services.

    • Granite Curbing installation.

    • Concrete Flatwork

    • Roadwork – Grading/ABC Stone


Aug. 1, 2022 - Aug. 31, 2022

We will continue to work on North Front Street between Grace Street and Chestnut Street.

Completed Work:

  • New water main and sewer main has been installed.

  • Temporary light posts have been installed.

  • Completed the two water main tie-ins at the Grace Street intersection.

  • Install RCP Storm Drain

Upcoming work for the month of August (Grace St. to Chestnut St.):

  • Begin advancing to the Walnut St Intersection

  • Connect/Switchover New Water Services

  • Electrical Work (Underground Wiring, Light Poles, etc.)

  • Continue to install Granite Curbs

  • Continue roadwork – Grading/ABC Stone

  • Asphalt Pavement

  • Asphalt Striping

  • Remove Pour House Steps

  • Demo Existing Sidewalks

  • Pour New Concrete Sidewalks

  • Install Brick Pavers

  • Irrigation & Landscaping

July 1, 2022 - July 31, 2022

We will continue to work on North Front Street between Grace Street and Chestnut Street.

Completed Work:

  • New water main and sewer main has been installed.

  • Temporary light posts have been installed.

  • Completed the two water main tie-ins at the Grace Street intersection.

Upcoming work for the month of July (Grace St. to Chestnut St.):

  • Install RCP Storm Drain

  • Connect/Switchover New Water Services

  • Electrical Work (Underground Wiring, Light Poles)

  • Install Granite Curbs

  • Roadwork – Grading/ABC Stone

  • Asphalt Pavement

  • Asphalt Striping

  • Remove Pour House Steps

  • Demo Existing Sidewalks

  • Pour New Concrete Sidewalks

  • Install Brick Pavers

  • Irrigation & Landscaping

June 20, 2022 - July 1, 2022

We will continue to work on North Front Street between Grace Street and Chestnut Street.

To date we have completed:

· Street demolition from the intersection of Chestnut St. to Grace St.

· New sewer main and services have been installed.

· New water main has been installed.

o New water services have been laid out but not connected.

Two-week look ahead:

· New water main and services will be chlorinated and tested.

o New water services to be reconnected to the meter.

· Electrical

o Disconnect and remove the two existing light post near the intersection of Grace St.

§ Temporary lighting will be installed.

o Install underground conduit

o Install a new ITS pole

· Begin installing new storm drain boxes and pipes.

· Perform two water main tie-ins in the Grace St. intersection (night work).