Jepson Parkway is an under construction new, four-lane continuous roadway serving the cities of Suisun City, Fairfield, and Vacaville. Starting from the Walters Road/SR-12 intersection in Suisun City, the planned 12 mile multi-modal corridor will take travelers all the way to the Leisure Town Road/I-80 interchange in Vacaville, providing a vital north-south county connection and relieving traffic on I-80. The completion of the project will help Solano County residents travel throughout the county, especially to important job sites and new neighborhoods, including:
The Jepson Parkway Concept Plan proposes two new bus routes to serve communities along the parkway.
An express shuttle between Fairfield-Vacaville Hannigan Station and Travis Air Force Base is also proposed.
As a multi-modal corridor, Jepson Parkway will also provide pedestrian and bicycle facilities. Most of the parkway will be accompanied by a 10 feet wide Class I bike path. However, Class II bike lanes will also be available along most of the route.
Class I: a separate path separate from the road dedicated for bike use only, may also permit pedestrians
Class II: a separate lane on the road dedicated for bike use only
Segment 10: Walters Road from East Tabor Avenue to SR-12 (2004)
I-80/Leisure Town Road interchange (2006)
Segment One: Leisure Town Road from Orange Drive to south of Poplar Road
Segment Two: Leisure Town Road from south of Poplar Road to Sequoia Drive
Segment Three: Leisure Town Road from Sequoia Drive to New Ulatis Creek
Segment Four: Leisure Town Road from New Ulatis Creek to Alamo Drive
Segment Five: Leisure Town Road from Alamo Drive to Vanden Road
Segment Six: Vanden Road from Leisure Town Road to Peabody Road
Segment Seven: Cement Hill Road from Peabody Road to Walters Road Extension
Segment Nine: Walters Road from Air Base Parkway to East Tabor Avenue
Segment Eight: Walters Road Extension from Cement Hill Road to Air Base Parkway
Current Status: completed
Begins south of the Vanden Road and Leisure Town Road intersection and ends north of the Elmira Road and Leisure Town Road intersection
Current Status: fully funded, design underway, construction expected to begin in 2021
Begins north of the Elmira Road and Leisure Town Road intersection and ends at the Sequoia Drive and Leisure Town Road intersection
Current Status: fully funded, construction expected to begin in 2021
Begins at Sequoia Drive and ends at Horse Creek 450 feet south of Orange Drive
Current Status: completed
Begins at the intersection of Peabody Road and Vanden Road and continues ~7000 feet north
Current Status: dependent on the conditions of the development agreement with the Train Station Specific Plan developer
Would realign part of the roadway to create a grade-separated crossing of the railroad
Current Status: to be completed by the City of Fairfield's developer, estimated cost of $7.5 million
Consisting of segments seven and nine, this phase will connect the improvements done by the City of Fairfield to those in Vacaville. This phase will widen the road to four lanes and add Class I bike lanes.
Phase Three would extend Walters Road from Cement Hill Road to Air Base Parkway; dependent on availability of funds