Eagle Times, May 24, 2025.
DES denies proposed construction and debris recycling facility
<Click to Expand>
By BOB MARTIN
Eagle Times Staff
CLAREMONT, N.H. ― The Department of Environmental Services (DES) denied the contentious
permit application by Acuity Management to build a facility at Recycling Services at 43 Industrial
Boulevard allowing for the collection of construction and demolition debris.
According to information provided to Claremont officials by DES, on Sept. 20, 2023, an
application was submitted by Recycling Services, Inc. to modify the facility’s permit to increase
the capacity from 50 tons per day to 2,750 tons per week averaged quarterly. There was also a
request to approve the acceptance of construction and demolition debris on top of the items
that are already permitted.
The application was amended multiple times due to DES requests for information, and on
March 15, 2024, Acuity applied for a waiver of some of the solid waste rules. Applications were
deemed completed on Sept. 24, 2024, and a public hearing that drew hundreds of people to the
Claremont Opera House was held on March 6, 2025. The deadline for public comments was
March 27, and after this the deadline for the DES decision was pushed to May 22.
There were several reasons for the denial listed by DES. State law requires the facility to be
designed to prevent entering and exiting vehicles from obstructing the safe flow of traffic on
public roads leading to or from the facility.
“The proposed Facility design will obstruct the safe flow of traffic on the public road, Industrial
Blvd, multiple times per waste haul truck,” the denial report by DES stated.
In this application, the facility would have trucks carrying waste driving east on Industrial
Boulevard and then turning left into 38 Industrial Boulevard. The trucks would then be weighed
and exit to go across the street to enter 43 Industrial Boulevard, and obstructed trucks would
queue until unloading at the tipping floor.
After unloading the trucks would leave, cross the street again to be weighed a second time. The
trucks would exit 38 Industrial Boulevard by turning right and driving west.
Workers would sort the waste to remove recyclable materials at 43 Industrial Boulevard, and
those materials would be stored there to be transported to recycling facilities. The non-
recyclable waste would have been loaded into rail cars to be taken to disposal facilities.
A truck queueing plan from August 2023 found that the trucks are about 35 feet long and travel
way of Industrial Boulevard is 22 feet wide. It was noted that each crossing would completely
obstruct the public road, and with 48 trucks per day over an eight-hour workday, there would be
about 96 complete road obstructions each day. It was also found that there would be additional
road obstructions as facility workers would also need to use entrances and exits.
The DES report added that a typical roll-off truck requires a turning radius of about 42 and 52
feet, and the available turning radius from Industrial Boulevard into the facility is up to about 30
feet. Crossing into oncoming traffic up to 96 more times would be necessary to operate the
facility, the report stated.
In total, the operation would have caused up to about 192 obstructions of traffic each day.
“The proposed operation would require public road usage of a nature and at a frequency that
will obstruct the safe flow of traffic on Industrial Blvd contrary to Env-Sw 1004.02(b),” the report
stated.
Another law requires the facility to “not interfere with the proper operation or closure of any
other facility.” The truck queuing plan showed that the proposed facility doesn’t have enough
queuing space to operate, and turning radii needs will require larger waste haul trucks. There
would be interference that would violate environmental laws, which requires the facility
operations “to be conducted in a manner as to accommodate on-site traffic flow in a safe and
efficient manner.”
The waiver requests were also denied, regarding a 50-foot setback. Currently the facility is
allowed to operate under an existing permit within 50 feet of the property, but the applicant
was proposing to increase the daily tonnage by a factor of 10 and also build new infrastructure
within the property line setback within 50 feet. This required Acuity to seek a waiver.
The report stated that the applicant had a proposed alternative to replace the existing building
with a new one that occupies “essentially the same footprint as the existing building.” It noted
that abutting properties to the north and south are owned by itself and a railroad company. It
stated that the new building would incorporate “improvements for better management of
existing and expanded facility operations,” and the proposal “will not result in an adverse effect
to the environment or natural resources of the state, public health, or to public safety.”
It was determined by DES that the application for a waiver did not meet the criteria needed.
The application has been several years in the works, involving various meetings, hearings, some
litigation, and an outpouring of opposition from concerned members of the public. Many of
these members are part of the group, A Better Claremont, who spoke out about the project
voicing concerns about pollution, the inability for Acuity to handle construction and demolition
debris at the site, and the “bad location for such an operation.” They released a statement
thanking DES for denying the application.
“DES listened to reason and did the right thing,” John Tuthill of Acworth and a member of ABC
said in the release. “Acuity’s proposal did not add up.”
Mayor Dale Girard, who is also a state representative, said the zoning board had worked with
the application and did not see that the proposal met the requirements of the area. He said he
did not feel this was the right location for this type of facility, which was something that the
zoning board and members of the public had previously voiced.
“Basically, DES’s response with the denial of the permit states that this is not a good location for
this type of project,” Girard said. “We appreciate the fact that people want to do business in the
city of Claremont, but we have to be able to do things in the right location for the citizens, as
well.”
Acuity Management has the right to appeal this decision within 30 days. A voicemail and email
were left with Acuity Management but not returned by deadline.
Valley News, March 4 2025
Public Hearing in Claremont <Click to Expand>
By Patrick O'Grady
CLAREMONT, March 6, 2025 — Speaker after speaker delivered the same message on Thursday night to officials from the state’s Department of Environmental Services: Deny the application for a construction and demolition recycling and transfer operation on Industrial Boulevard.
Close to 400 people attended the state’s hearing on the proposal, which residents contend would be harmful to the environment, public health and the city’s infrastructure.
“You have the power to stop this,” resident Nelia Sargent told DES officials at the more than three-hour hearing at the Claremont Opera House wound down. “We do not want this. You can defend and protect us.”
The more than 60 people who spoke, including business owners, state representatives and city officials, repeatedly urged DES to uphold its mission of protecting the state’s residents and the environment by denying the application. Their comments were repeatedly met with loud applause. “No, means no,” and “No is a complete sentence,” several speakers said. See the Complete Article