Completing their work in April, 2025, a small dedicated group planned and flagged a potential route for the Rim Country Connector Trail from Red Rock Spring to Payson. The goal is to form a regional trail system, connecting Payson to the Highline National Recreation Trail, which serves as the backbone of the future 104-mile network.
Volunteers spent many months analyzing and scouting a viable location for a single-track trail between Pine and Payson. Many alternate routes were scouted and rejected for various reasons. The final proposed route, shown as a red line in the map below, totals 20 miles.
It is designed as a sustainable trail, striving for no more than 5% grades. In a few locations this guideline is exceeded out of necessity, but not many and not for very far. In its entirety, the Rim Country Connector is located on Tonto National Forest land. It will be constructed as a Class 3 trail, suited for use by hikers, mountain bikers and equestrians and will provide a unique, world-class trail experience and venue for future recreational events. a unique, world-class trail experience and venue for future recreational event
The second map below shows the western portion of the 104-mile regional trail network. Both the renovated Highline Trail (violet line) and the Pine Loop (light blue line) were completed in the spring of 2025, opening 84 miles of the network to public use. The 20-mile Rim Country Connector will follow by 2030, after its National Environmental Policy Act (NEPA) review is completed and construction can begin.
A first step in the NEPA process will be a cultural resources survey by a third-party archaeologist, at an estimated cost of $30,000. Rim Country Trail Fund seeks donations to cover the cost of this required survey.
On April 10, 2024, the Payson Area Trail System Trailhead and Access Plan was approved by Payson Town Council. The full plan can be viewed here, and below are some highlights.
Houston Mesa Trails are an in-progress expanded system of sustainable trails that take advantage of the US Forest Service fuel break currently being constructed around the NE area of Payson.....These trails will eventually connect Payson to the Rim Country Connector Trail, and on to the Highline Trail and Pine/Strawberry FR trails north of Payson at the base of the Mogollon Rim.
Boulders Area Trail System (BATS) is one of the Rim Country’s most magnificent geological areas. Located within the Tonto National Forest and bordering Payson and Star Valley, its majesty is found in the Granite Dells, a backdrop for balancing boulders, and hillside trails of Ponderosa Pine, Chaparral, and Pinyon Juniper found throughout Stewart’s Pocket and the winding Stewart Creek.
Nestled in a quiet neighborhood, a locally recognized access point to BATS became a popular, yet unexpected destination for thousands, growing exponentially after 2020.
Though acknowledged as part of Payson Area Trails System (PATS) since 1998, the area was traversed mostly by social trails, with the exception of Boulders Loop and Cypress Trail. Due to its increasing popularity, the Payson Ranger District authorized the Boulders Area Trail System, Phase 1, on August 21, 2024, as the Tonto National Forest’s first sanctioned trail system within the PATS master plan.
On May 28, 2025, in a unanimous vote, Payson’s Town Council approved allocating $296,670 for the design and engineering of two proposed BATS trailheads as part of PATS, in partnership with the National Forest Foundation. Access to both the Cypress and Boulders trailheads will be off Granite Dells Road on a section previously serving as a Forest Service road.
This project will include
Cypress Trailhead with limited amenities including parking for 20 vehicles for day-use only.
Granite Dells Trailhead with parking for 30 vehicles for day-use only and amenities including an informational kiosk and a vault toilet.
6 miles of new non-motorized, Class 3 trails.
Adoption and maintenance of existing social trails.
Implementation of a new trail signage plan.
Restriction of motorized intrusions along Granite Dells Road and the trails.
With work on the design and engineering underway, RCTF seeks donations for the construction of the two trailheads. Estimated construction costs of both trailheads is $2 million, which is anticipated to be funded by a combination of grants (RCTF Board members are busy submitting multiple grant applications, in partnership with the USFS and the Town of Payson), corporate sponsorships and private donations. We welcome corporate adoptions of the many amenities these trailheads will feature (informational kiosk, seating, signage, etc.)