Progress Update
50-60 Workers on site.
Civil Work happening on Tapas IF7-IF8 and IF9-IF12. Manual mixing of concrete and manual lifting to higher floors causing slow work.
Some amount of interior work in Tapas IF17-IF20
Exterior works happening around Surya Towers:
Painting
Lobby preparation for Block C and Block A
Planting of grass and plants near B Block entry
Some brick work was going on on 1 or 2 floors.
Raheja Developer really need to get more workers on site (500 - 800) under proper management / supervision to have any hope of handing over this project in the next 2-3 years. The quality of interior works is suffering as well due to the start- stop and unplanned nature of work.
Surya Tower From Highway Side
Surya Tower From Aravalli Side
Literally Gone To The Dogs
Club House Area incomplete Basement Slab
IF21-IF32 (back lane)
IF 21 - IF 24
IF 47 - IF50
IF47-IF50
IF45-46
IF43-IF44
IF41-IF42
IF43-IF50
Looking back to try and locate IF32A, IF32B, IF33, IF34, IF35 & IF36. Where are they??
Missing Club House and incomplete Basement Slab
Club House Area
STP Plant work stalled for the past 3-4 months
IF1 - IF2B
IF3-IF8
IF1-IF8 (back lane)
"On start of Flooring" milestone for which demand was raised in 2015-2016. Completion was not on the agenda once money collected.
Water in all Tapas lift wells
Water in all Tapas lift wells
IF20-IF15 (Most Complete of the Tapas)
IF14-IF9 (Getting there structurally)
IF20-IF15 (front lane)
IF19-IF20 (entrance)
Looks like Picasso's work
No Glands while termination of conduits in boxes
Tiles to be laid awaiting workers
Some non standard connections in the plumbing pipes
Raheja Developers taking "Green Building" too literally!
EWS Apartments