PhP 76.41B
Parcellary Survey Plans for Packages 3 and 4 were approved last October 2024.
Right of Way Action Plan (RAP) Report was approved on 15 May 2023.
Parcellary Survey Plans for Package 1 is for approval.
Detailed Engineering Design (DED) Plans for Packages 1, 3 & 4 are for approval.
Additional Pay Items Subscripts and Conditional Pay Items of Works for Packages 1, 3 & 4 are for approval.
Notice of Award was issued and conformed by the consultant on December 19 2024.
UPMO-RMC1 (B) requested for obligation for the advance payment of Consulting Services under GAA 2023 Extended last December 26, 2024.
Contract Perfection for Consulting Services is ongoing.
PhP 32.74B
Feasibility Study was completed last January 31, 2024.
The documentary requirements indicated in the National Economic and Development Authority- Investment Coordination Committee (NEDA-ICC) Checklist of New Project Proposals was submitted last October 7, 2024 for their review and approval.
The Department received the Preliminary Report and comments of NEDA-ICC Secretariat last November 2024.
DPWH responses to the NEDA-ICC Secretariat’s comments to be submitted on January 2025.
DPWH currently preparing responses to the NEDA-ICC Secretariat’s comments and planning submission of document this January 2025.
PhP 10.77B
Short span bridges and approaches including the Dauis Interchange and Tagbilaran Rotunda located at Bohol Mainland and Panglao Island sides as funded under the FY2018, FY2020 & FY2023 GAAs were already completed.
Funding for the main bridge or the remaining spans through ODA is already confirmed by the NEDA Board.
PhP 94.07B
Segments 1, 2 & 3B will be implemented through PPP mode by the Cebu Provincial Government.
The implementation of Segment 3A is being handled by DPWH Regional Office VII but is suspended due to a CDO issued by DENR-EMB7 in relation to a landslide/ ground movement affecting a certain section. DPWH RO7 is currently finalizing the plans for the immediate rehabilitation of the affected section in conformity with the agreements/dialogues with DENR EMB7 and concerned LGU’s.
Lapu-Lapu Coastal Road
Length: 4.17 km. coastal road
Location : Province of Cebu, Region VII
Indicative Project Cost : Php 76.413 Billion
Funding Source : FS – Grant Financing under KEXIM
Proposed Schedule : FS: December 15, 2023 – October 22, 2024
Project Objectives: Address increased traffic demand and relieve traffic congestion by constructing a coastal road linking three bridges between Mandaue City and Lapu-Lapu City; and Enhance local connectivity and promote economic development through improved mobility within the project area.
Project Status:
DPWH presented the Project Profile to KEXIM in April 18, 2023.
DPWH submitted through April 27, 2023 letter the Project Concept Paper to KEXIM.
DPWH in May 24, 2023 letter requested for the inclusion of Environmental and Social Impact Assessment (ESIA) to be funded under grant assistance through a letter.
Ongoing Feasibility Study (FS) under Grant which started December 15, 2023 to be completed in October 2024.
Kick-off Meeting/1st Coordination Meeting held January 4, 2024.
1st site visit conducted January 17, 2024.
Courtesy Call to Lapu-Lapu City Mayor, Hon. Junard Chan, held January 18, 2024.
2nd Coordination Meeting between RMC1(B) and Yooshin JV done March 12, 2024.
2nd Site Visit held March 13, 2024
Completed Traffic Survey (May 7-10, 2024)
Ongoing Topographic Survey and Geotechnical Investigation Survey