Preliminary Project Previews
For Contractor Use
For Contractor Use
KEY PROJECT HIGHLIGHTS
The Utah Department of Transportation (UDOT) is designing Phase 2 of Mountain View Corridor (MVC), between Porter Rockwell Boulevard in Herriman and Old Bingham Highway in West Jordan.
Improvements will include a concrete freeway segment with two general purpose lanes (for a total of four lanes), grade-separated cross streets and slip ramps connecting to the existing divided highway.
The project will construct 25 bridges at 16 different locations
ANTICIPATED SCHEDULE
October 2024 - Project Preview #1
March 2025 - Project Preview #2
July 2025 - Project Preview #3
Spring 2026 - Project Preview #4
Summer 2026 - Project Preview #5
January 2027 - Project Advertisement
February 2027 - Pre-Bid Meeting
Spring 2027 - Begin Construction
Fall 2030 - Complete Construction
QUESTIONS/COMMENTS
Send questions to mountainview@utah.gov or call (385) 386-8439
Project Manager, Oanh Le-Spradlin
(801) 975-4819 or oanhle@utah.gov
Last updated: 7/3/2025
ALL INFORMATION PROVIDED IN UDOT PROJECT PREVIEWS IS FOR INFORMATION ONLY. ALL INFORMATION-ONLY MATERIAL IS NOT PART OF THE CONTRACT DOCUMENTS AND WILL NOT BE RELIED UPON. THE DEPARTMENT ACKNOWLEDGES THAT CONTRACTORS MAY ELECT TO USE THE INFORMATION AT ITS DISCRETION; HOWEVER, BOTH PARTIES AGREE THAT THE DEPARTMENT HAS NOT ANALYZED, GATHERED, OR DEVELOPED THE INFORMATION FOR ACCURACY OR SUFFICIENCY FOR USE, AND IT MAY INCLUDE ERRORS, OMMISSIONS, INCONSISTENCIES, INACCURACIES, DEFICIENCIES OR OTHER DEFECTS.