look ahead
Here is a look at the work we are doing around the campus this week and the work planned for the near future.
Here is a look at the work we are doing around the campus this week and the work planned for the near future.
THIS WEEK
THIS WEEK
FEb 3rd - feb 7th
FEb 3rd - feb 7th
- Structure :
- CEP :
- Commissioning
- Tower Enclosure :
- Metal panel
- Canopy
- Interior :
- Level 2 Punch
- Level 3 final paint and flooring
- Level 4 Above Ceiling Rough-in
- Level 6 final paint and flooring
- North Connector
- Ceiling grid
- East Connector
- Parking Garage :
- Final punch
- North Loop Road :
- South Connector
- Ceiling grid
NEXT WEEK
NEXT WEEK
feb 10th- feb 14th
feb 10th- feb 14th
- Structure :
- CEP :
- Commissioning
- Tower Enclosure :
- Metal panel
- Canopy
- Interior :
- Level 2 Punch
- Level 3 final paint and flooring
- Level 4 Above Ceiling Rough-in
- Level 6 final paint and flooring
- North Connector
- Ceiling grid
- East Connector
- Parking Garage :
- Final punch
- North Loop Road :
- South Connector
- Ceiling grid
project milestones
project milestones