District: Faubourg Marigny - Full Control
Owner: Frenchmen Decatur LLC
HDLC Staff: Dennis Murphy
Rating: Significant
Applicant: Heather Cooper
Permit #: 20-48205-HDLC
Description: Final detail review of previously approved renovation of an existing Significant rated three-story, mixed-use building including partial roof demolition and construction of a new rear addition.
Previous ARC Recommendations & Commission Actions:
10/04/23: The Commission voted to grant conceptual approval of the application with the final details, including elevator overrun relocation, to return for additional ARC review once further developed.
09/19/23: The ARC voted to recommend conceptual approval with the final details and revised elevator overrun location to return for additional ARC review once further developed. The ARC also agreed that:
The proposal has improved considerably from the previous review, the amount of overall roof demolition has been substantially reduced, and the ARC appreciated that the current iteration preserves more of the existing view of the historic gable roof forms at the rear.
The applicant should confirm the type of elevator equipment necessary to ensure the overrun at the roof is reduced in height as much as possible. The ARC also recommended the applicant consider relocating the elevator, so the overrun is less visually prominent, such as by moving it to the opposite side of the 3rd floor hallway or to the area of new infill construction.
08/02/23: The Commission voted to defer action on the request to appeal the ARC recommendation for denial so the applicant could have additional time to reconsider the proposed third-floor roof alterations and to provide updated drawings reflecting a significant reduction in the overall amount of roof demolition for additional ARC review.
06/20/23: The ARC voted to recommend denial of the application. The ARC agreed the proposal has improved substantially since the initial review and they appreciated the time and effort the applicant has committed to modify the design, reduce its overall visibility, and to be more compliant with the HDLC Guidelines. However, the proposed work to convert the existing attic space into usable square footage still involves substantial removal and modification of the existing historic roof form and building fabric and is not considered appropriate based on the Significant rating of the building and the visibility of the proposed changes from Esplanade Avenue. Additionally, the overall amount of roof demolition and encapsulation to create the proposed interior connection at the 3rd floor may be slightly more than shown on the current roof demolition plan.
04/06/23: The Commission voted to deny the request to appeal the ARC recommendation for denial because the existing roof form is still intact, is visible, and continues to read visually as a historic roof from several points in the surrounding public right of way. Additionally, the proposed amount of roof demolition is not considered appropriate based on the HDLC Guidelines and the Significant rating of the building. City Council appeal submitted.
03/14/23: The ARC voted to recommend denial of the application. The ARC agreed the existing historic building’s roof forms and parapets are visible from several areas in the public right of way, particularly along Esplanade Avenue, and the proposal involves too much destruction of the Significant rated building’s roof structure and historic building fabric. The ARC also noted that the proposed addition appears to be handled well architecturally, but the amount of overall roof demolition is too high and cannot be recommended for approval based on the HDLC Guidelines.
02/01/23: The ARC voted to defer the application for additional review to allow time for the applicant to coordinate a site visit with Staff and ARC members present. The ARC agreed the removal of the previously proposed rooftop penthouse was a positive development, however, they expressed concern the proposal still entails the demolition of most of the existing Significant rated building’s historic roof structure. The ARC also agreed that:
While the current roof may have been modified in the past and may pose challenges for contemporary waterproofing and usable interior square footage, the form of the roof is still intact, is visible, and continues to read visually as a historic roof from several points in the surrounding public right of way, particularly from Esplanade Avenue.
The proposed parapet modifications for the increase in third-floor floor-to-ceiling height may also be partially visible from Esplanade Avenue.
A section drawing or additional photos demonstrating the constraints at the third floor and additional 3-D perspective views to better illustrate the proposed rear addition and its visibility from Esplanade Avenue should be provided for the next review.
The ARC also agreed a site visit would be helpful to better understand the current condition of the roof and the visibility of the roof and proposed rear addition from Esplanade Avenue.
09/07/22: The Commission voted to deny the request to appeal the ARC recommendation for denial of the new rooftop penthouse addition because the existing roof form is directly related to the historic use and typology of the building and the proposed addition would eliminate this historic condition, would negatively impact the significance and visual integrity of the building, would be highly visible from multiple points in the surrounding public right of way, and because the HDLC Guidelines specifically prohibit rooftop additions on Significant rated buildings.
08/03/22: The Commission voted to defer action on this application until the following meeting, per the applicant request.
07/19/22: The ARC voted to recommend denial of the application. The ARC also agreed that the design revisions presented were an improvement over the previous iteration. The additional setback of the penthouse helps to decrease its overall visibility, but it remains a highly visible addition from various points in the surrounding public right of way. The ARC also noted that the existing roof form is directly related to the historic use and typology of the building and that the proposed addition would eliminate this historic condition. The ARC also agreed the proposed penthouse addition does not retain the character-defining feature of the roof form, would negatively impact the significance and visual integrity of the existing building. Additionally, the ARC noted they cannot recommend approval for the penthouse because it does not meet the HDLC Guidelines which specifically prohibit rooftop additions on Significant rated buildings.
04/06/22: The Commission voted to deny the request to appeal the ARC recommendation for denial. Applicant submits City Council appeal of Commission denial. City Council requests applicant revise proposal to meet previous ARC recommendations and re-submit for re-review.
03/09/22: The Commission voted to defer action on this application until the following meeting, per the applicant request.
11/16/21: The ARC voted to recommend denial of the application because the installation of rooftop additions on significant rated buildings is prohibited by the HDLC Design Guidelines. The ARC also agreed that:
The location of the relocated HVAC equipment is an improvement and it does not appear that they will be visible from a surrounding public right of way.
The door and window openings on the rooftop addition are vulnerable to the elements and a small canopy or overhang at this location could be useful in keeping them protected from water intrusion. Additionally, it is preferred that this type of element be integrated into the overall penthouse design now rather than added in the future as this may also increase the overall visibility of the penthouse. The ARC recommended installing a simple 18” projecting horizontal element above the doors and windows for this purpose or by further recessing the windows and doors more deeply into the wall depth.
In terms of the color and materiality of the rooftop addition, darker colors are better than lighter colors and a less reflective surface is preferable. The ARC also recommended considering an alternative material other than stucco for the rooftop addition so that it is further differentiated from the existing historic structure, for example, metal panels.
The rooftop addition should be further set back from the Esplanade Avenue side so that it becomes less visible from the Avenue.
The ARC reiterated that they believe the rooftop addition will be highly visible from both Elysian Fields Avenue and Decatur Street and that as such it was not an appropriate addition to the existing Significant rated structure.
10/19/21: The ARC voted to defer this application for additional review. The ARC agreed that the proposal had been improved by setting the penthouse addition further back on the existing historic structure. The ARC also recommended:
The mechanical equipment indicated at the roof of the penthouse may be visible from the surrounding streets and should be relocated to the lower roof such that they are not visible.
Wind-driven rain could pose a problem for the penthouse door and window openings and the ARC recommended considering simple awnings or an overhang for cover.
Reducing the 11'-9" overall height of the penthouse addition so that it is less visible from the surrounding streets.
The applicant should include some additional analysis of the view from Chartres Street for the next design review.
The ARC reiterated that they cannot make a recommendation for approval for the proposed work because the HDLC Design Guidelines prohibit the installation of rooftop additions on Significant rated structures and this application will require additional review and approval from the full Commission.
12/15/20: The ARC voted to defer this application for additional review. The ARC noted they cannot make a recommendation for conceptual approval because the Design Guidelines (12:13) do not permit the construction of rooftop additions on Significant rated buildings. They recommended the applicant consider revising the design such that the rooftop addition is not visible from any surrounding public right of way, and as such would not require HDLC approval. The ARC also requested the applicant receive NPS (application Part 2) comments and feedback before returning for additional design review.
* DATE indicates Commission review
Current - Proposed Elevator Overrun Location
Previously Reviewed - Proposed Elevator Overrun Location
Current - Proposed Perspective View from Elysian Fields Avenue
Previously Reviewed - Proposed Perspective View from Elysian Fields Avenue
Current - Proposed Roof-Mounted Equipment Plan
Current - Roof Demolition Plan - 39.6%
Current - Proposed New Roof Plan
Previously Reviewed - 06/20/23 - Roof Demolition Plan - 54.6%
Previously Reviewed - 03/14/23 - Roof Demolition Plan - 100.0%
Current - Rear Perspective View from Elysian Fields Avenue
Previously Reviewed - Rear Perspective View from Elysian Fields Avenue
Proposed Roof Demolition Plan - 54.6%
Proposed New Roof Plan
Existing Roof Demolition Plan
Proposed New Roof Plan
1885