District: Faubourg Marigny - Full Control
Owner: 1030 St Anthony LLC
HDLC Staff: Dennis Murphy
Rating: Unrated
Applicant: Alexander Adamick
Description: New construction of a 1,870 SF 1-1/2 story, single family residential building including new construction of 1,130 SF two-story rear residential accessory building on a vacant lot.
Previous ARC Recommendations:
04/18/23: The ARC voted to defer the application for additional review. The ARC also agreed that:
The overall site plan is appropriate, and the rear accessory appears to be only minimally visible from the street.
Stucco is an appropriate building cladding material for the front building, but the applicant could also consider weatherboards or another more contemporary material.
The parapet walls extending out to the street from the face of the building should be eliminated.
The proposed dormers and their detailing appear awkward, and the applicant should consider eliminating them from the front roof or using a more contemporary language and materials.
The ARC also recommended the applicant consider additional dormer and/or roof form options for presentation at the next review.
The front entry door alcove should be enhanced so it is wider and more prominent.
The proposed windows should be operable and additional information on window types, detailing, and installation (such as depth in wall) should be provided for the next review.
For example, the first-floor elevation windows could be operable above a fixed panel for a contemporary “Juliette” style balcony in a more contemporary language.
The side elevation windows at the front building should be studied further and refined.
A context drawing should be provided for the next review that accurately depicts the existing adjacent buildings on the block face, so the ARC can better evaluate the proposed massing, foundation height, fenestration, etc.