GH-Bid-001 - Street Improvements Phase 1 ($2 million)

  • Resurface Music Street and install median between Glissando Avenue and BFC Way
  • Bring crosswalks at Music Street and Glissando Avenue up to code
  • Remove portion of railway tunnel

GH-Bid-002 - Street Improvements Phase 2 ($2 million)

  • Remove railway tunnel between Music and Musique Streets
  • Resurface and add median to Glissando Avenue between Music and Musique Streets

SM-Bid-001 - Upgrades Phase 1 ($1 million)

  • Expand playground
  • Upgrade fencing
  • Construct access walkway to playground
  • Install modular classroom

SM-Bid-002 - Modular Classroom Removal

  • Convert existing Kindergarten classroom into special education classroom
  • Remove modular classroom

SM-Bid-003 - Upgrades Phase 2 ($2 million)

  • Re-plaster interior walls on existing classroom building
  • Re-construct south facade to allow all classrooms to be same size
  • Upgrade lighting in existing building
  • Move Kindergarten Playground to opposite side of building - remove fencing
  • Remove exterior doors on west side and install exterior doors on east side

SM-Bid-004 - Upgrades Phase 3 ($8.4 million)

  • Construct new 3-story classroom and administration building adjacent to Music Avenue
  • Re-route existing tram tracks and road under new building
  • Demolish existing former administrative annex
  • Expand former administrative annex to new property boundary
  • Construct new expanded library and new music room in former admin annex
  • Excavate additional sub-basement level
  • Construct new multi-purpose room under original building footprint
  • Construct new parking facility and kitchen under former admin annex footprint
  • Construct entrance to parking facility via basement of new building
  • Install new upgraded elevator in main classroom building
  • Construct new grass Kindergarten Playground
  • Expand existing playground to be bounded by Music Avenue and Spruce Mountain Street
  • Install new fencing and blacktop

MS-Bid-001 - Construction of School

  • Construct entirety of school as per original plans

HS-Bid-001 - Construction of School

  • Construct entirety of school as per original plans

DO-Bid-001 - Construction

  • Construct new District Administration and Facilities Office
  • Terraform land as needed