Progressive Design-Build
Client: Currituck County
Engineering Partner: Kimley-Horn
Construction Partner: T. A. Loving
Delivery Method: Progressive Design-Build
Driven by development within the existing collection system and along the NC 168 corridor as well as residential developments, Currituck County is going to increase the size of the existing Moyock Regional WWTP Package Plant and High-Rate Infiltration System.
This project aligns with the 2008 Moyock Centralized Sewer Master Plan which seeks to address the projected increase in wastewater flow through 2030.
This project includes the design, permitting and construction of the expansion project.
Major Milestones
30% Design Complete - On Hold for VE Options
60% Design Complete - On Hold for VE Options
Start Construction
Early Works - 01/02/2026
Main Plant - Est. 08/31/2026
Construction Complete - Est. December 2027
November 2025 Progress Update
Disposal Early Works Design Complete
Early Works Estimating in Progress
VE Options being pursued for Main Plant