Progressive Design-Build
Client: Currituck County
Engineering Partner: Kimley-Horn
Construction Partner: T. A. Loving
Delivery Method: Progressive Design-Build
Driven by development within the existing collection system and along the NC 168 corridor as well as residential developments, Currituck County is going to increase the size of the existing Moyock Regional WWTP Package Plant and High-Rate Infiltration System.
This project aligns with the 2008 Moyock Centralized Sewer Master Plan which seeks to address the projected increase in wastewater flow through 2030.
This project includes the design, permitting and construction of the expansion project.
Major Milestones
30% Design Complete - September 2025
60% Design Complete - November 2025
Start Construction - Est. April 2026
Construction Complete - Est. November 2027
May 2025 Progress Update
Site Visits Complete
Additional survey is being done to pickup wells and bores
Hydrogeo in progress
March 2025 Progress Update
Contract Executed
Survey Started
Initial Design Kickoff Held
Reviewing Technology Selection