To write a change order, describe the extra or changed work in plain language, list the added cost and any change to the schedule, reference the original quote or contract, and get the customer's signature before you start the new work. A clear change order protects both sides: the customer knows what they're paying for, and you get paid for work that wasn't in the original scope.
Small contractors and solo trades often skip change orders because the extra job seems minor, or because it feels awkward to bring up money mid-project. Those unwritten "while you're here" jobs are one of the most common reasons a profitable job ends up barely breaking even.
This is general business information, not legal advice. Contract and consumer rules vary by location, so check what applies to your trade and area.
Project and customer details: name, address, and the original quote or contract number and date.
Change number: "Change Order #2" makes multiple changes easy to track.
Description of the change: what's being added, removed, or done differently. Be specific: "Replace 3 rotted subfloor sheets in hallway (approx. 96 sq ft)," not "floor repair."
Reason: customer request, hidden condition found, or material substitution.
Price: labor, materials, and any other costs, with the new total for the change.
Schedule impact: how many days the change adds, if any.
Updated contract total: original amount, previous changes, this change, and the new total.
Payment terms: whether it's due now, at the next payment stage, or at completion.
Signatures and date: yours and the customer's.
Write a change order any time the work, price, or timeline is different from what the customer approved. Common triggers:
The customer asks for something extra ("Can you also do the closet?").
You find a hidden problem, like rot, old wiring, or a leak behind a wall.
A material is unavailable and you need to substitute.
The customer wants to remove part of the work, which should lower the price.
The best habit is simple: no signature, no extra work. If the customer is unreachable and stopping would cause damage, document what you found with photos and notes, and get written approval as soon as you can.
Change orders are where margins quietly slip. Price them as carefully as the original job:
Include the hidden costs: extra trips, setup and cleanup, disposal, and time spent ordering parts.
Use your actual rates: the same labor rate and markup as the main job, not a "friend price" because you're already there.
Check the profit: know your cost and your margin on the change before you quote it.
Don't absorb small changes silently: if you want to do something as goodwill, write it on the change order at $0 so the customer sees its value.
Keep the tone factual and friendly. Explain what changed and why, show the price, and let them decide. "We found water damage under the tile. Here are photos. Replacing the subfloor adds $640 and one day. Want us to go ahead?" Customers usually appreciate clarity; it's surprises at the final invoice that cause disputes.
ScopeBid lets you add mid-job extra work as a change order with its own price and its own profit impact, so you can see what the change does to your margin before you send it. It generates PDF quotes and invoices with your logo, terms, and payment details, keeps internal costs and margins off customer documents, and supports in-person signature acceptance. Approved quotes convert to invoices, and you can record deposits and partial payments and track the balance. It also works offline, with no account required.
ScopeBid is free with in-app purchases. Your first 3 quotes are free with full PDFs; ScopeBid Pro (a subscription) removes the quote limit and unlocks job costing and the full invoicing workflow. ScopeBid records payments but doesn't process cards or move money, and it isn't accounting or tax software.
It's strongly recommended. A signed change order is the clearest record that the customer approved the extra work and price; requirements vary by location and contract.
Generally only if the customer agreed to it. That's why getting a written, signed change order before doing extra work matters.
It depends on your contract. Many contracts treat unforeseen conditions as a change that the customer approves and pays for; spell this out in your terms.