City of Harvard Infrastructure Committee Recommends Hot-In-Place Recycling for Timber Drive and Deliberates Sidewalk Expansion.
City of Harvard Infrastructure Committee Recommends Hot-In-Place Recycling for Timber Drive and Deliberates Sidewalk Expansion.
The City of Harvard's Infrastructure Committee convened on September 9, 2025, to discuss crucial road, sidewalk, and bridge projects, ultimately making recommendations that will be presented to the City Council on September 23, 2025.
A significant portion of the meeting focused on the future of Timber Drive, a main thoroughfare in the Shadow Creek subdivision, characterized by multi-family housing and a low Pavement Condition Index (PCI) of 22-26. Public Works Director Rob Lamz and City Engineer Gary Rozwadowski presented three options for rehabilitation:
Remove & Replace (R&R)
2-inch Mill & Resurface (M&R)
Hot In-Place Recycling (HIPR)
City staff recommended Hot In-Place Recycling (HIPR) for Timber Drive. The committee agreed, passing a motion with a 3-1 vote to forward this recommendation to the city council.
HIPR involves heating and recycling existing asphalt in place, applying a rejuvenator, and then adding a new 1.5-inch surface layer. This method is estimated to cost approximately $254,751, a mid-range option compared to $414,938 for Remove & Replace and $242,377 for Mill & Resurface. Proponents noted that HIPR would add to the street's crown, helping with water drainage on the currently flat road (0.6% slope). It also addresses underlying base issues through skip patching, providing a longer service life (10-15 years) than mill and resurface, while being more cost-effective than a full rebuild.
Committee members also saw Timber Drive as a valuable "test bed" to evaluate HIPR technology for potential future use across the city's road network. The project, including engineering and contracts, is anticipated to occur in spring 2026, as winter is too close for immediate construction.
The committee also engaged in a lengthy "sidewalk to sidewalk" discussion, primarily concerning reconstruction plans for streets like McKinley Street, which lacks comprehensive sidewalks. City Engineer Gary Rozwadowski clarified that while "sidewalk to sidewalk" is the goal and framework for reconstructed streets under the city's "complete streets" resolution, staff, committee, or council have the discretion to adapt plans based on specific circumstances, such as existing hardscaping, trees, or the presence of sidewalks on only one side. There was general agreement on the importance of having at least one sidewalk per street for pedestrian safety, especially near public amenities like the hospital and library.
Regarding Marengo Road and its bridge, an update was provided on the backlog for the bridge project. Construction for the Marengo Road bridge is now most likely set for 2027, delayed from an earlier 2026 projection for the lining. Phase two plans for Marengo Road have been approved, and IDOT approval is pending for the bridge's phase two design contract, indicating that the projects remain closely aligned despite the delay. Other ongoing sidewalk projects mentioned include Phase 2 of the Marengo Road - Ayer Street sidewalk and Route 173, with Phase 1 of Route 14 recently signed.
A large portion of the meeting concentrated on the future of Timber Drive, a major street in the Shadow Creek subdivision.