Total Budget: RM1.2–1.55 billion (estimates vary by source)
New Handling Capacity: Increase from 6.5 million to 12 million passengers per year
Tech Integration: Introduce Airport 4.0 systems—automation and smart technology
Passenger Experience: Enrich terminal aesthetics with a “Sense of Malaysia” feel
The expansion is structured into three phases, further divided into three Work Packages (WPs):
Phase 1 / WP1
Ancillary buildings: ATC tower, CAAM office, virtual tower, M&E, civil & ICT systems
Awarded to Gagasan Maya (RM107.9 m); ~31% complete as of Feb 2025, on track to finish by Nov 2025
Phase 2 / WP2
Airside improvements: apron expansion, taxiways, drainage, utilities
Contract with Acre Works (RM254.6 m); 24% completion reported Oct 2025
Phase 3 / WP3
New terminal build + existing terminal renovation, roads, landscaping, HV/LV relocation
In design stage; tender out May 2025 (~RM1.2 b) with candidates Gamuda, IJM, MRCB, SunCon; completion set for 2027–2028
Apron Works Plan: Complements airport upgrade through four detailed phases:
Phase 1 (1 Mar 2025 – 15 Jul 2025): Wide-body bay expansion
Phase 2 (16 Jul 2025 – 15 Oct 2027): Apron expansion
Phase 3 (16 Oct 2027 – 1 Aug 2029): Taxiway rehabilitation
Phase 4 (2 Aug – 2 Dec 2029): Taxiway realignment
Remote Digital Virtual Tower (RDVT): Southeast Asia’s first implementation at PIA via WP1
Design Consortium: NEAPOLI, Ainul Rahman Architect (ARA), and Arup—took part in masterplan and initial design, targeting LEED/GreenRE/GBI certification
Package 3 Bidders: Gamuda, IJM, MRCB, and SunCon among front-runners.
WP2: ~24% complete
WP3: Design phase, with contractor bid closing May 2025; operations expected in 2027
Security & Immigration: Installation of 10 additional auto-gates each at international halls; deployment of 30 additional Immigration personnel
LRT Integration: Coordination with MRT Corp to build a Light Rail Transit station near the terminal
The PIA expansion is a comprehensive upgrade split into three major packages. Progress on WP1 and WP2 is strong, while WP3 is gearing up. The project—designed to double capacity, enhance airside operations, and improve passenger experience—is on schedule for full operational readiness by 2028, with phased terminal services as early as 2027.