Avoid these Common Pitfalls when Building a Home and Save Some Money
Many clients think permits are only a few hundred dollars.
Reality: Between impact fees, building permits, utility hookups, and engineering reviews, Utah clients can be out $15k–$40k before digging a hole.
Excavation, grading, retaining walls, and utility trenching are often underestimated.
Rocky Mountain Power, Dominion Energy, and water districts charge hookup/connection fees that can run thousands, especially in rural areas.
Clients don’t realize they may need to pay for extending utilities to the lot if it’s not fully serviced.
In Utah, a geotech/soils report is almost always required.
If expansive clay or poor soils are found (common in Utah Valley), it can mean costly foundation upgrades (piers, over-excavation, engineered fill).
Homeowners rarely budget for this.
Clients think they can swap finishes freely, but every change ripples through subcontractors, schedule, and budget.
Allowances (e.g., $15k for cabinets) are often misunderstood as “that’s exactly what I’ll pay” — when in reality, upgrades or customizations can easily double the cost.
Homeowners expect a fixed, short timeline.
Weather (snow in Utah winters, spring mud), subcontractor availability, inspections, and material lead times all cause delays.
A “12-month build” can become 14–16 months without anyone doing anything wrong.
Many clients think their construction loan functions like a normal mortgage.
In reality:
The bank pays the builder in draws after inspections.
Client must cover interest-only payments during construction.
If change orders go over budget, client may need out-of-pocket cash before bank funds more.
Clients assume passing inspections = perfect quality.
Truth: Inspectors only check for minimum code compliance, not craftsmanship.
Warranty or punch list items are separate and often misunderstood.
Many think landscaping is part of the “home build.”
In Utah, unless contracted, landscaping, fences, sprinklers, and driveways beyond the apron are not included. These can run $20k–$100k+.
Homeowners expect the house to be “perfect” at move-in.
Reality: Builders close once the house is substantially complete, with a punch list to follow.
Some things (paint touch-ups, seasonal adjustments on concrete, HVAC balancing) happen after move-in.
Clients often assume “my land, my rules.”
Many Utah subdivisions have utility easements, setbacks, and strict HOA design rules that limit where and what can be built (driveway width, outbuildings, exterior colors).