Overview
December 2021 Purchase property
March 2022 Clear dead trees & ground fuel
April 2022 Survey
May 2023 Cabin design
August 2023 Fire Department permit
September 2023 TCPUD Sewer Permit
October 2023 Submit EDC building permit application
March 2024 Electrical Service Application
July 2024 Building permit approved
July 2024 Site clearing & excavation
August 2024 Foundation
October 2024 Winterization
March 2025 Fabricate timber frame
April 2025 Sill plates & ponywalls
May 2025
Wall drainage, seal, backfill
Central column footers
Basement walls & slab
June 2025
Central beam
Floor joists & sheathing
Raising the timber frame
July 2025
External wall framing & sheathing
Roof T&G
August 2025
Roof rafters, & sheathing
Porch timber frame
Remaining Projects (out of order)
Porch/Decks
-kitchen deck
-stairs, railing & bottom pad
-reposition N deck joists winter 2025-26
-T&G on N deck roof winter 2025-26 CS
-N deck railings winter 2025-26
-E deck piers
-E deck structure
-E deck railings
-N & E deck decking
Roof
-fire sprinkler pipes & drops
-roof mineral wool insulation
-roof foam insulation & sealing
-roof sheathing & underlayment
-metal roof
Water
-trench to SE corner
-incoming pipe & domestic valve
-under-floor piping
-risers & supply-line stubs
-fire system at control room
Sewer
-trench, pipe, and connections
-pipes to fixtures (kitchen, bath, W/D)
-vent system
Windows & Doors
-research & order winter 2025-26
-cut & tape openings
-sills & sealing openings
-exterior bucks
-head flashing
Exterior Insulation & Cladding
-corrugated metal under decks winter 2025-26
-window & door bucks
-horizontal 2x
-vertical battens
-corner trim
-siding material
Floors
-insulation between floor joists R19
-seal subfloor at posts winter 2025-26
Interior Stairs & Walls
-stair posts & stringer winter 2025-26
-stair treads and landing winter 2025-26
-bedroom walls framed winter 2025-26 CS
-stairway walls framed winter 2025-26
-insulation R23 (after electric & plumbing)
Fire sprinkler system
-Patterson estimate
-meet with Steve @ Hydrofire
Grading, Landscaping, & BMPs
-remove foundation excavations
-grade south side and build retaining wall
-dripline drainage & infiltration
-parking pad infiltration box
-perimeter drainage infiltration box
Heating
-pad for heat pump
-lines to head unit(s)
-electrical connections