KEY PROJECT HIGHLIGHTS
SR-177 (West Davis Corridor) currently runs from Farmington to SR-193. From Farmington to a point just south of 700 South in Syracuse, the corridor is a divided freeway with two lanes in each direction. Between 700 South and SR-193, the road narrows to one lane in each direction and is no longer divided. This project will extend SR-177 as a four-lane divided freeway from 700 South up to 1800 North (SR-37).
Elements of construction include:
Roadway and trail construction with asphalt paving
Highway bridge construction at 700 S, SR-193, 300 N, 800 N, and 1300 N
Pedestrian bridge construction at SR-193 and 200 S
Park and ride at 1800 North
Drainage improvements
Utility relocations
Noise walls
Signs and striping
Signals, ITS, and lighting
Landscaping and erosion control
ANTICIPATED SCHEDULE
Early 2026 Project Advertisement & Prebid Meeting
Spring 2026 Begin Construction
Summer 2028 Complete Construction
QUESTIONS/COMMENTS
Send questions to Corey Nelson at coreynelson@utah.gov or call (385) 251-4134
Last updated: 10/14/2025
ALL INFORMATION PROVIDED IN UDOT PROJECT PREVIEWS IS FOR INFORMATION ONLY. ALL INFORMATION-ONLY MATERIAL IS NOT PART OF THE CONTRACT DOCUMENTS AND WILL NOT BE RELIED UPON. THE DEPARTMENT ACKNOWLEDGES THAT CONTRACTORS MAY ELECT TO USE THE INFORMATION AT ITS DISCRETION; HOWEVER, BOTH PARTIES AGREE THAT THE DEPARTMENT HAS NOT ANALYZED, GATHERED, OR DEVELOPED THE INFORMATION FOR ACCURACY OR SUFFICIENCY FOR USE, AND IT MAY INCLUDE ERRORS, OMMISSIONS, INCONSISTENCIES, INACCURACIES, DEFICIENCIES OR OTHER DEFECTS.