Step by Step instructions:
Step 1 - Go onto the Online Permits System and apply for a Pre-Application Meeting.
Step 2 - After you apply for a Pre-Application Meeting and you receive a PA-##### you will need to schedule an Owner/Developer Meeting with UDOT to discuss options and feasibility. This is held typically before an engineer is on board and before the property is purchased. IF you have an engineer on board, please have them attend this meeting. (Please scroll to the blue section to schedule this meetings after you apply for the PA#)
Step 3 - Schedule an Engineer Meeting, this is where UDOT will go over what is needed to be shown on the plans. UDOT will also go over all required documents that will be required for the submittal. If you skipped Step 2 and are going straight to the Engineers Meeting you will need to apply for a Pre-Application Meeting online and get a PA-##### before we can hold this meeting. (Please scroll to the blue section to schedule this meeting)
Step 4 - Once the plans are ready and you have all the required documentation for the submittal, you will schedule a Redline Meeting to go over the plans and all required docs to verify they are ready. Plans must be uploaded to your google Redline folder at least 24 hours in advance. (A complete submittal will need to be submitted within 5 days of the redline or a new redline might need to be scheduled.) (Please scroll to the blue section to schedule this meeting)
Step 5 - Make all necessary changes that were requested at the Redline meeting. Once changes are made you will upload a complete submittal to your google project folder 1st Submittal within 5 days of the Redline Meeting.
Scheduling a Meeting:
Before UDOT can hold any of the following meetings, you will need to go to the UDOT Website and apply for a Pre-Application Meeting. There you will receive a PA-#####. You will need to enter this number in the comment sections when you schedule any of the meetings below.
Meeting 1 - To schedule an Owner/Developer Meeting please click on one of the following links.
This meeting is to discuss options and feasibility. You do not need an engineer or a concept for this meeting. This meeting is typically held as early as the due diligence phase.
To meet in person click here. (Tuesday and Thursday)
To meet virtual click here. (Monday - Thursday)
Meeting 2 - To schedule an Engineer Meeting please click on one of the following links.
Your Civil Engineer is required to attend this meeting. We will give them your list of required documentation and go over any questions they may have.
To meet in person click here. (Tuesday and Thursday)
To meet virtual click here. (Monday - Thursday)
Meeting 3 - To schedule a Redline Meeting please click on one of the following links.
Your Civil Engineer is required to attend this meeting. You are required to have uploaded your complete set of plans and variance (if required) into your google Redline folder at least 24 hours before your scheduled meeting or you will be asked to reschedule.
To meet in person click here. (Tuesday and Thursday)
To meet virtual click here. (Monday - Thursday)
Follow-up Meeting - To schedule a Follow-up Meeting please click on one of the following links.
This meeting is held at request only. This meeting is not required.
To meet in person click here. (Tuesday and Thursday)
To meet virtual click here. (Monday - Thursday)
If you would like to meet in person and can't meet in person on a Tuesday or Thursday please let me know and we can accommodate you. ntreweek@utah.gov
Docs (Download):