University of Minnesota

Samuel C. Lind

Lind Hall

(U of M Lind Hall Renovation)

CONSTRUCTION UPDATE

UPDATED: 11/04/22



Disruption Avoidance Alerts

  • Truck Deliveries for Furniture - Path and space, Oct-Nov

  • Truck Deliveries for Department Moves - Path and space, Oct - Jan 2023



Overall Project Schedule

  • Abatement process (3rd floor/2nd floor, basement, sub-basement, exterior windows): June 2021 - November 2021


  • Construction:

- Lower Level - December 2021 - August 2022

- 2nd floor: November 2021 - August 2022

- 3rd floor: August 2021 - August 2022

- 4th Floor - Complete August 2022

  • Site and exterior work: May 2021 - August 2022

  • Project closeout: August 2022 - October 2022

  • Furniture and A/V Install: September 2022 - November 2022

  • Departments Move-in: November 2022 - December 2022

  • Taylor Center and Starbucks open: Janurary 2023

  • Open for Classes: January 2023

Renovation on Existing Building Renderings

UPDATE: Site Logistics

Church St. pedestrian is now open with no barriers (except for minor deliveries/work in that lane) Be aware.

Scholars Walk

Addition and pathway to the Scholars Walk are complete.

CONSTRUCTION UPDATES

COMPLETED

    • Department Moves: CSE - 1st floor

    • Department Moves: Student Org - LL


ONGOING

    • Lower-level painting

    • FFE Installation

    • Washing

    • Card and key access

UPCOMING

  • Department Moves: CS&E - 3rd Floor

  • Department Moves: PC Lab, and Help Desk - Lower Level

  • Exterior add-ons, sidewalk repairs, and lighting on the East courtyard.

ADDITIONAL POTENTIAL DISRUPTIONS

  • Signs and safety cones are being misplaced/taken. Remain aware of Lind Hall's construction area and respect the safety protocols (walk bikes in Church Street, watch for flag-person, distance yourself from fenced areas, etc.)

WEEKLY PROGRESS PHOTOS

Monthly Building Status

updated info on the week of 10/31/22

/

Sub-Basement North and South:

Complete

Lower Level:

Ceilings

Bench seating area

IT Help Desk

Painting

1st Floor:

• New Scope Adds

2nd Floor:

• Film installation remaining

• Signage installation remaining


3rd Floor:

Film installation remaining

• Signage installation remaining


4th Floor:

Complete


Exterior:

• ​Fencing down

• ​Link complete

• Tuckpointing complete

Can you name this preserved historic room/space in Lind Hall?


Taylor Center, "once the Engineering Library—now houses a new computer lab that is already drawing about 200 students a day! The Taylor Center is named in honor of George “Bill” Taylor, a 1934 mechanical engineering graduate" (UMN, CSE news). Recently renovated, it's existing oak carries throughout the lab showcasing its historic character.


Collaborative Design Group

James O'Shea - Principal & Project architect

Mortenson Construction

Travis Heilig - Superintendent
Avin Kallenbach- Senior Project Manager

UMN Capital Project Management

Paul Oelze - Construction Project Manager

UMN CSE

Andrew G. Alleyne - Dean