Curb Ramp Construction - COMPLETED as of 04/20/2026
Milling & Paving
Paving COMPLTED as of 08/13/2026.
Final pavement striping will begin August 14, weather permitting.
Prime Contractor: M&B Asphalt Company
Subcontractors: RMH Concrete (Curb Ramps & Sidewalks) & ARL (Striping)
Contract Amount: $1,250,644.79
Contract Completion Date: September 4, 2026
Achre Court
Brace Avenue
Circular Street (Market Street to Perry Street)
Colony Avenue
East Market Street (Frost Parkway to Greenfield Street)
Hancock Street (Prospect Street to Summit Street)
Kensington Avenue
Main Street (Schonhardt Street to Greenfield Street)
Miami Street (Birchwood Drive to Nelson Street)
Nile Street
Oil Street (Market Street to Perry Street)
Parkview Drive
Pinecrest Drive
Railroad Street (Tilden Street to Clinton Avenue)
Tilden Street
Veterans Memorial Parkway
Walker Street (Prospect Street to Summit Street)
Walnut Street
(*) The contract amount also includes sidewalk upgrades, paving and striping within City Parking Lot #4. All costs associated with the work within this parking lot will be paid via funds from the City's Capital Improvement Fund. The total cost for this work came out to $88,080.97.
See the Frequently Asked Questions page above or call or email the City Engineer's Office at the contact information provided below