ISSUANCE OF BUILDING PERMIT
A BUILDING Permit is required prior to the construction, erection, alteration, major repair, or renovation or conversion of any building/structure owned by government of private entities.
The permit becomes null and void if work does not commence within one year from the date of such permit, or if the building or work is suspended or abandoned at any time after it has been commenced for a period of 120 days.
Office or Division: Office of the Municipal Engineering
Classification: Medium
Types of Transaction: G2B- Government to Owners
Who may avail: Building Owners
PROCESS
STEP 1
SECURE APPLICATION FORM
Fees to be Paid: None
Processing Time :10 minutes
Person Responsible:
Engr II, Engineering Assistant
STEP 1.1
SUBMIT REQUIREMENTS
AGENCY ACTION
Verifies and check the documents submitted.
Fees to be Paid: None
Processing Time :25 minutes
Person Responsible:
Engr II, Engineering Assistant
Municipal Engineer
AGENCY ACTION
Validate the completeness of the requirement.
Fees to be Paid: None
Person Responsible:
Engr II, Engineering Assistant
Municipal Engineer
AGENCY ACTION
Evaluates plans as to Structural, Architectural, Electrical, Mechanical, Sanitary/Plumbing for assessment.
Fees to be Paid: None
Person Responsible:
Engr II, Engineering Assistant
Municipal Engineer
AGENCY ACTION
Issues order of payment.
Fees to be Paid: None
Person Responsible:
Engr II, Engineering Assistant
Municipal Engineer
STEP 2
PAYS ORDER OF PAYMENT
AGENCY ACTION
Call the Applicant
Fees to be Paid: None
Processing Time :15 minutes
Person Responsible:
MTO Staff and Receiving Counter
AGENCY ACTION
Get the receipt
Fees to be Paid:
NBC Building Permit fees
Electrical Permit Fees
Plumbing Permit Fees
Processing Time :15 minutes
Person Responsible:
MTO Staff and Receiving Counter
STEP 3
ENDORSEMENT FOR FIRE SAFETY INSPECTION
AGENCY ACTION
Issue Certificate of Final Electrical Inspection
Fees to be Paid: None
Processing Time :5 minutes
Person Responsible:
Engr II, Engineering Assistant
STEP 4
ISSUANCE OF APPLICATION PERMIT
AGENCY ACTION
Issue Building permit, Electrical, and Plumbing Permit
Fees to be Paid: None
Processing Time :5 minutes
Person Responsible:
Engr II, Engineering Assistant
TOTAL:
Fees to be Paid: Application for Electrical Permit Processing Time: 40 minutes