Mini Project Question: Construction of a Residential Building
Title:
Preparation of Detailed Estimate, Rate Analysis, and Specifications for the Construction of a G+1 Residential Building
Objective:
To prepare a comprehensive estimate, rate analysis, and specification document for the construction of a two-storey (G+1) residential building using the Short Wall–Long Wall Method, Centre Line Method, and RCC Component Estimation principles.(Use any one method for calculation)
Project Description:
Redraw given drawing from feet, inches to meter:
You are required to prepare the detailed estimate, abstract of cost, and rate analysis for the construction of a G+1 residential building having the following features.
Refer to given drawings.
Tasks to be Performed:
Part A – Quantity Estimation
Study the provided building drawings (Plan, Elevation, Section).
Compute quantities for all items of work:
Earthwork in excavation and filling
PCC bed
Brick masonry in foundation and superstructure
RCC work in footing, column, beam, and slab
Plastering, flooring, doors, and windows
Use Short Wall–Long Wall method and Centre Line method for verification.
Prepare the abstract of estimated cost.
Part B – RCC Component Estimation
Estimate quantities of concrete and reinforcement for ( one element ):
RCC slab
RCC beam
RCC column
RCC footing
Prepare bar bending schedule (BBS) for major RCC elements.
Part C – Rate Analysis
Perform rate analysis for:
Earthwork excavation
Brick masonry
RCC works (slab, beam, column)
Plastering
Flooring
Include Direct and Indirect Costs, overheads, and contractor’s profit.
Part D – Specifications
Write general specifications for building works.
Write detailed specifications for at least five items:
Earthwork
Brickwork
RCC work
Plastering
Flooring
Part E – Additional Components
Prepare an estimate for a manhole and septic tank for the same building by assuming 5 number of people in each building.
Prepare summary and conclusions.
Mini project report format (Submission Format):
Your mini-project report should include:
Title Page (Same as your project report)
Objectives
Drawings (Plan, Section, Elevation)
Quantity Estimation Sheets
Abstract of Cost
Rate Analysis Tables
Specifications (General & Detailed)
RCC Component Estimation & BBS
Roadwork and Sanitation Estimates
Attach Draft format : Agreement between owner and contractor for the given project.