PB ZOO KOALA EXHIBIT
Project Start: 4/15/2010 Early Completion: 6/4/2010 (50 days)
South View
North View
5/14/2010 - Day 30 - Roof installed; interior completion & MEP to begin
5/5/2010 - Day 21 - Roof framing started
5/4/2010 - Day 20 - Tie beams complete, formwork stripped
5/3/2010 - Day 19 - Tie Beams ready for inspection & pour
4/29/2010 - Day 15 - Storefront beam pour (2nd masonry lift scheduled for 4/30/2010)
(yes, that is a Peacock in the picture & they enjoy Supervising the construction all fluffed up)
4/27/2010 - Day 13 - Storefront beam
4/23/2010 - Day 9 - Masonry 1st lift
4/21/2010 - Day 7 - Strip Forms & Masonry Delivery
4/20/2010 - Day 6 - Slab Pour
4/19/2010 - Day 5 - Foundation/Slab Ready for Inspection