Ready to Move Forward
Pictures we will need for your project.
All breakers in Electrical Panel(s) with breakers readable.
Main Breakers (able to read the breaker size).
Main Panel Label (if available)
Main panel from Street. This will have the design team know how to run electrical conduit and if we need to coordinate with NV Energy on location of disconnects and other equipment.
Roof surface we plan on installing solar on. This allows us to see if there are any roof vents or areas that may cause installation issues.
The Process
Contract Signature
HOA Submission (we help you with the paperwork) - HOA's have 45 days to review, but can not legally stop you from installing solar.
Design / Engineering / Blueprints
Submission to Building Department for Permit
Installation (Most take 2 - 3 days, larger systems can take longer)
Building Department Inspection
Net Metering Submittal
Meter Installation (can take 4 weeks from net metering submittal)
Turn the system on!