Facilities Projects/ Updates

Welcome to the Wilson School District Facilities Projects Site. 


A central hub for information about facilities initiatives across the District.


 Currently, we are working on two construction phases at Wilson:


This platform will provide regular updates on all District construction projects.  Be sure to check back frequently for the latest updates!

TOP UPDATES

Proposed Lincoln Park Elementary School

The Wilson School District has been assessing and monitoring enrollment over the past few year and we have come to a place where it has become necessary to address the overcrowding in our elementary schools.


Temporary measures, such as using portable classrooms, helped manage enrollment increases to some extent. However, we now find that constructing a sixth elementary school is essential to meet the educational requirements of our students.


Following an extensive exploration of options for constructing this new elementary school, we have concluded that building a cutting-edge facility on the Lincoln Park property owned by the District is the most advantageous choice for all stakeholders involved. Therefore, in August 2023, the Wilson School Board authorized Crabtree, Rohrbaugh & Associates to embark on the schematic design phase for the new Lincoln Park Elementary School and the investigative processes for design development.


In March, 2024 the School Board authorized the next stage of the design process. Since that time, we were presented with a revised timeline for both the Lincoln Park and Southern Middle School Project.  See below for an update on that revised timeline as well as a visual representation of the project key dates.


As previously communicated, a timeline was established indicating the school would be ready for occupancy at the outset of the 2026-2027 school year. However, recent developments have necessitated a reevaluation of our projected timeline. We have discovered that a significant increase in permit applications for construction projects has delayed our district's ability to obtain the necessary permits for bidding purposes by approximately six months.


As a result, we now anticipate that the school will be completed in late spring or early summer of 2027. This revised timeline indicates that the school will likely be ready for opening in the 2027-2028 school year.


Continue to consult this website for the latest Lincoln Park Elementary School/ Southern Middle School project information.

Updated Time Line for Lincoln Park Elementary School/ Southern Middle School Renovation Project

Thank you to everyone who attended our Community Information Session about the proposed Lincoln Park site on Wednesday, February 28 at 6 pm in the District Administration Office, 2601 Grandview Blvd., West Lawn.  

Presentation Link HERE  Watch the event recording HERE

New Wilson School District Performing Arts Center-- COMING in 2025!

Sample New Auditorium/ Gym Entrance

Sample Lobby Design

Sample Lobby Design

Sample Lobby Design

Sample Lobby Design

Sample Auditorium Design

Sample Auditorium Design