A museum is a connect to the history, a connect to peoples beliefs and a collection of them.
A space that preserves such valuables and memories the space as well should have a connect with the people.
The site is in Paithan, which is famous for its paithani sarees.Â
The process of weaving these, the zari work that is used of gold and silver threads in weaving was quite interesting how a metal is used in a cloth. so I thought of including the process of this paithani making in the museum, instead of just displaying them, one can walk n involve themselves in the process of making the paithanis.Â
On the site there is the Jayakwadi dam on west and temples on north east n east, so by drawing axes which would be open that helped in visual connectivity also the winds are mainly from west and north west so the structure is lower on the west and goes higher on the south east and south so that it does not block visual connections and air flow.
The climate in Paithan is hot and and dry, so keeping this in mind I started jotting down different strategies that would help tackle this. So hierarchy of spaces i.e. closed, open, semi open etc. which can be brought in by corridor verandas courtyards etc. plantations and maybe water bodies that filter light and air and also dehumidify during wetter times. Use of fins and louvers and recessed windows could be done to get adequate light. I thought of Brick as material as it would response well to the climate and the context.Â
Aim was to build a space where you are constantly in connect to the outside. So I started working with courtyards at different levels to form overlooking spaces, these were the earlier diagrams where I tried to open up spaces to outside and manage the movement of people.
The axonometric shows the whole experience of the space.
I thought of keeping public areas on lower floors and cabins n administrative spaces on the higher.
All these closed spaces would be connected to outside by pathways with a pergola above it, verandas and adjustable fins.
COVER PAGE
SITE DEVELOPMENT PLAN
SETTING OUT PLAN
FOUNDATION PLAN
GROUND FLOOR PLAN
FIRST FLOOR PLAN
SECOND FLOOR PLAN
THIRD FLOOR PLAN
TERRACE CUT PLAN
ROOF PLAN
SOUTH ELEVATION
EAST ELEVATION
SECTION AA'
SECTION BB'
EXTERNAL WALL SECTION
TOILET DETAILS
STAIRCASE PLAN N DETAILS
STAIRCASE SECTIONS
DOOR DETAILS AND SCHEDULE
WINDOW DETAILS AND SCHEDULE
Identifying datum followed by Triangulation method
Connecting points to form the basic lineout on site
Using ropes tying it to form grid on site
Defining the excavation pit
Excavation for load bearing walls
Brick foundation for load bearing walls
Tying the columns together using plinth beams
Plinth 0.6m above the ground level
Constructing Ground floor walls
Similarly moving towards the upper floors