Ground Breaking Ceremony held February 28, 2019
Courtyard Storm Drainage, Administrative Building Foundation, Cafeteria/Building A/Building K Addition Foundation dirt work, and Building C/Building B Foundation dirt work begun
Courtyard Storm Drainage, Administrative Building Foundation, Cafeteria/Building A/Building K Addition Foundation work
Cafeteria/Building A/Building K Addition Foundation work, Administrative Building Framing, Building A, B, C, and K Sprinkler System Installation
Administrative Building Addition, Fire Sprinkler System in Existing Classroom Buildings, Foundation for Cafeteria/Classrooms Expansion
Administrative Building Addition, Fire Sprinkler System in Existing Classroom Buildings Paint/Lighting/Ceiling, Foundation for Cafeteria/Classrooms Expansion, Dirt Work for BC Classroom Addition
Administrative Building Addition, New Ceiling/Lighting in Existing Cafeteria Building, Foundation for Cafeteria/Classrooms Expansion, Dirt Work for BC Classroom Addition, New Sidewalk between Building K and Nurse's Office
Administrative Building Addition, New Hallway Flooring in Buildings A, B, C, and K, Foundation for Cafeteria/Classrooms Expansion, and Dirt Work for BC Classroom Addition
Administrative Building Addition, Foundation for Cafeteria/Classrooms Expansion, and Dirt Work and Plumbing for BC Classroom Addition
Interior of Administrative Addition, Exterior Brick of Building A and K Addition, Foundation for Building B and C Addition
Interior of Administrative Addition, Exterior Brick of Building A and K Addition, Foundation for Building B and C Addition, Excavation work for Building A and B Addition