Search this site
Embedded Files
Skip to main content
Skip to navigation
20231010 Project Update Director's Review
Home
QA/QC
Review Information
Zoom
Presentations
Previous Reviews & Recommendations
Management
ES&H and WPC
Recovery Organization
Cost and Schedule and Risk
ASO and Commissioning
NB IRR
Training and Qualification
Quantitative Safety Analysis
Operations Envelope
SAD, ASE, and Summary Hazard Analysis
Institutional Accelerator Safety Program
Q&A
Local Area Information
20231010 Project Update Director's Review
Home
QA/QC
Review Information
Zoom
Presentations
Previous Reviews & Recommendations
Management
ES&H and WPC
Recovery Organization
Cost and Schedule and Risk
ASO and Commissioning
NB IRR
Training and Qualification
Quantitative Safety Analysis
Operations Envelope
SAD, ASE, and Summary Hazard Analysis
Institutional Accelerator Safety Program
Q&A
Local Area Information
More
Home
QA/QC
Review Information
Zoom
Presentations
Previous Reviews & Recommendations
Management
ES&H and WPC
Recovery Organization
Cost and Schedule and Risk
ASO and Commissioning
NB IRR
Training and Qualification
Quantitative Safety Analysis
Operations Envelope
SAD, ASE, and Summary Hazard Analysis
Institutional Accelerator Safety Program
Q&A
Local Area Information
2023 Project Update Director's Review
Cost, Schedule and Risk
Note: The cost and schedule data provided in this review is based on the August 2023 close.
Schedule Files - August Close (.pdf)
Schedule Files - August Close (.
xer
)
Cobra Files
Responsibility Assignment Matrix
NSTXURP RAM - August 2023.pdf
VARs
Select Baseline Change Proposals
EVMS Reports
CPR1 Files
Risk Register
Uncertainty Matrix
Uncertainty Table - September 2023 DR Register.xlsx - Google Sheets.pdf
Monthly Risk Reports
PEP Cost Table Comparison
DR Financial Data - PEP Table 10:3:23.pdf
August 2023 Bottoms Up EAC Spreadsheet
AUGUST 2023 EACs_Final
PPPL EVMS Information
Risk Management Plan
NSTXU_1_PLAN_100, R10 - NSTX-U RECOVERY PROJECT RISK MANAGEMENT PLAN.pdf
Basis of Estimate Document
NSTXU_1_DOC_103, R7 - NSTX-U RECOVERY PROJECT BASIS OF ESTIMATE.pdf
NSTX-U Recovery CAMs use the
CAM Notebook
for their daily work.