Philadelphia E&T has developed an aggressive timeline for project completion. We are looking forward to opening in Fall of 2022, welcoming the Class of 2026 to begin their high school career at our new facility.
Students who will have school in the new facility:
Current 11th Graders (Class of 2023)
Current 10th Graders (Class of 2024)
Current 9th Graders (Class of 2025)
NEW STUDENTS FOR 2022-2023 (Class of 2026)
TIMELINE
September 15, 2021- Purchased Property
October 12, 2021- Pre-Bid Meeting for Construction Bidding
November 8, 2021: Bids Due
November 19, 2021: Board of Trustees Awarded Bids
December 1, 2021: Construction Began
February 23, 2022: Furniture Ordered, Per Approval of Board on January 21, 2022
February 24, 2022: Pre-Bid Meeting for Construction Bidding (Low Voltage, Shades, Rolling Gate)
March 10, 2022: Bids Due
March 25, 2022: Board of Trustees Awarded Bids
UPCOMING DATES
Estimated: July 30, 2022: Construction Completion
Estimated: September 1, 2022: Building Open